Skip to main content

CPWD Analysis of Rates · Drainage

Constructing soak pit 1.20x1.20x1.20 m filled with brickbats including S.W. drain pipe 100 mm diameter and 1.20 m long complete as per standard design

Item number
19.33
Analysis basis
Details of cost for one soak pit
Priced inputs
7
Derived rate
2,890.10 / one soak

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.33 Constructing soak pit 1.20x1.20x1.20 m filled with brickbats including S.W. drain pipe 100 mm diameter and 1.20 m long complete as per standard design — is derived from 7 priced inputs for one soak and works out to ₹2,890.10 per one soak after water charges, GST, CPOH and cess. The full build-up is below.

  • Earth work in excavation including
  • disposal of surplus earth 1.2x1.2x1.2m =
  • 1.73 cum
  • 1.2x1.2x1.2 = 1.73 cum
  • Second class brick edging laid length
  • wise with half brick depth
  • For filling brick bats
CodeInputUnitQuantityRate (INR)Amount (INR)
(Rate as per item no. 2.8.1 of SH: Earth work)Rate as per item 2.8.1Sub-analysiscum1.73260.30450.32
0362Brick batsMaterialcum1.73525.00908.25
Rate as per item no. 16.8.1 of SH : Road workRate as per item 16.8.1Sub-analysismetre5.253.45277.94
1854Stoneware pipes grade A (60 cm long) 100 mm diaMaterialeach277.00154.00
9999SundriesMaterialL.S.25.842.2758.66
0114BeldarLabourday0.5736.00368.00
9999SundriesMaterialL.S.13.522.2730.69
TOTAL
2,247.86
Add 1 % Water charges on “W-A”
15.20
TOTAL
2,263.06
Add GST on “X-A” (multiplying factor 0.2127)
326.45
TOTAL
2,589.51
Add 15% CPOH on “Y-A”
279.19
TOTAL
2,868.70
Add Cess @ 1% on “Z-A”
21.40
Cost of one soak pit
2,890.10
Say
2,890.10

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1775. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works