Constructing soak pit 1.20x1.20x1.20 m filled with brickbats including S.W. drain pipe 100 mm diameter and 1.20 m long complete as per standard design
- Item number
- 19.33
- Analysis basis
- one soak
- Priced inputs
- 7
- Derived rate
- ₹2,890.10/ ONE SOAK
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.33 (Constructing soak pit 1.20x1.20x1.20 m filled with brickbats including S.W. drain pipe 100 mm diameter and 1.20 m long complete as per standard design) is derived from 7 priced inputs for one soak and works out to ₹2,890.10 per one soak after water charges, GST, CPOH and cess. The full build-up is below.
- Earth work in excavation including
- disposal of surplus earth 1.2x1.2x1.2m =
- 1.73 cum
- 1.2x1.2x1.2 = 1.73 cum
- Second class brick edging laid length
- wise with half brick depth
- For filling brick bats
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | (Rate as per item no. 2.8.1 of SH: Earth work)Rate as per item 2.8.1 | cum | 1.73 | 260.30 | 450.32 | |
| 0362 | MAT | Brick bats | cum | 1.73 | 525.00 | 908.25 |
| SUB | Rate as per item no. 16.8.1 of SH : Road workRate as per item 16.8.1 | metre | 5.2 | 53.45 | 277.94 | |
| 1854 | MAT | Stoneware pipes grade A (60 cm long) 100 mm dia | each | 2 | 77.00 | 154.00 |
| 9999 | MAT | Sundries | L.S. | 25.84 | 2.27 | 58.66 |
| 0114 | LAB | Beldar | day | 0.5 | 736.00 | 368.00 |
| 9999 | MAT | Sundries | L.S. | 13.52 | 2.27 | 30.69 |
- TOTAL
- 2,247.86
- Add 1 % Water charges on “W-A”
- +15.20
- TOTAL
- 2,263.06
- Add GST on “X-A” (multiplying factor 0.2127)
- +326.45
- TOTAL
- 2,589.51
- Add 15% CPOH on “Y-A”
- +279.19
- TOTAL
- 2,868.70
- Add Cess @ 1% on “Z-A”
- +21.40
- Cost of one soak pit
- 2,890.10
- SAY
- ₹2,890.10
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1775
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1775. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.