Skip to main content
R/DAR 2023

Constructing soak pit 1.20x1.20x1.20 m filled with brickbats including S.W. drain pipe 100 mm diameter and 1.20 m long complete as per standard design

Item number
19.33
Analysis basis
one soak
Priced inputs
7
Derived rate
₹2,890.10/ ONE SOAK
D-01/RATE ANALYSISITEM 19.33

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.33 (Constructing soak pit 1.20x1.20x1.20 m filled with brickbats including S.W. drain pipe 100 mm diameter and 1.20 m long complete as per standard design) is derived from 7 priced inputs for one soak and works out to ₹2,890.10 per one soak after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Earth work in excavation including
  • disposal of surplus earth 1.2x1.2x1.2m =
  • 1.73 cum
  • 1.2x1.2x1.2 = 1.73 cum
  • Second class brick edging laid length
  • wise with half brick depth
  • For filling brick bats
ANALYSIS OF RATES · ITEM 19.33DETAILS OF COST FOR ONE SOAK PIT
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUB(Rate as per item no. 2.8.1 of SH: Earth work)Rate as per item 2.8.1cum1.73260.30450.32
0362MATBrick batscum1.73525.00908.25
SUBRate as per item no. 16.8.1 of SH : Road workRate as per item 16.8.1metre5.253.45277.94
1854MATStoneware pipes grade A (60 cm long) 100 mm diaeach277.00154.00
9999MATSundriesL.S.25.842.2758.66
0114LABBeldarday0.5736.00368.00
9999MATSundriesL.S.13.522.2730.69
BUILD-UP TO RATE
TOTAL
2,247.86
Add 1 % Water charges on “W-A”
+15.20
TOTAL
2,263.06
Add GST on “X-A” (multiplying factor 0.2127)
+326.45
TOTAL
2,589.51
Add 15% CPOH on “Y-A”
+279.19
TOTAL
2,868.70
Add Cess @ 1% on “Z-A”
+21.40
Cost of one soak pit
2,890.10
SAY
₹2,890.10
D-02/SOURCEPRINTED PAGE 1775
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1775

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1775. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDRAINAGE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.