Making soak pit 2.5 m diameter 3.0 metre deep with 45 x 45 cm dry brick honey comb shaft with bricks and S.W. drain pipe 100 mm diameter, 1.8 m long complete as per standard design

With common burnt clay F.P.S. (non modular) bricks of class designation 7.5
Item number
19.32.1
Analysis basis
one soak
Priced inputs
14
Derived rate
₹26,861.90/ ONE SOAK
D-01/RATE ANALYSISITEM 19.32.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.32.1 (Making soak pit 2.5 m diameter 3.0 metre deep with 45 x 45 cm dry brick honey comb shaft with bricks and S.W. drain pipe 100 mm diameter, 1.8 m long complete as per standard design With common burnt clay F.P.S. (non modular) bricks of class designation 7.5) is derived from 14 priced inputs for one soak and works out to ₹26,861.90 per one soak after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Earth work in excavation including disposal of surplus earth 3.14/4x(2.5)²x3m =
  • 14.73 cum
  • = 3.14/4x(2.5)² x 1.5 m = 7.37 cum
  • 2nd class bricks
  • perimetre = 4x0.35 =1.40 m
  • Area = 1.40x2.925 m = 4.1 sqm
  • Number of brick = 4.1x487x0.066 =
  • 131.78
  • Wastage 10% = 13.718
  • Total= 144.96 Say 145 numbers
  • Brick bats = 3.14/4x(1.2)²x2.925m =3.33
  • cum
  • Net qty= 2.74 cum
  • Brick aggregate 50 to 80 mm nominal
  • size = 3.14x1.50x0.03x2.925 m = 4.13
  • cum
  • Brick aggregate 40 mm nominal size
  • = 3.14x2.15x0.35x2.925 m =6.91 cum
  • Carriage of brick bats and aggregate
  • Precast R.C.C.slabs 7.5 cm thick in
  • cement concrete 1:1.5:3 (1 cement : 1.5
  • coarse sand : 3 graded stone aggregate
  • 20 mm nominal size)
  • 0.45x0.45x0.075 m = 0.02 cum
  • Reinforcement @ 80 kg/cum = 0.02x80
  • =1.6 kg
  • 2nd class brick edging laid length wise
  • with half brick depth
  • 3.14x2.6 m =8.17 m
  • Deduct = 0.45x0.45x2.925 m = 0.59 cum
ANALYSIS OF RATES · ITEM 19.32.1DETAILS OF COST FOR ONE SOAK PIT
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per item no. 2.8.1 of SH: Earth workRate as per item 2.8.1cum14.73260.303,834.22
2602MATCommon burnt clay F.P.S. (non modular) bricks class designation 7.51000 Nos0.1454,724.00684.98
0362MATBrick batscum2.74525.001,438.50
0285MATBrick Aggregate (Single size) : 63 mm nominal sizecum4.13700.002,891.00
0287MATBrick Aggregate (Single size) : 40 mm nominal sizecum6.91700.004,837.00
1854MATStoneware pipes grade A (60 cm long) 100 mm diaeach377.00231.00
9999MATSingle matting 2.5x2.5 m = 6.25 sqmL.S.112.142.27254.56
SUBRate as per item no 5.12 of SH : RCCRate as per item 5.12cum0.0210,585.90211.72
SUBRate as per item no. 5.22.6 of SH : RCC workRate as per item 5.22.6kg1.6107.85172.56
SUBRate as per item no. 16.8.1 of SH : Road workRate as per item 16.8.1metre8.1753.45436.69
0123LABMason 1st classMason 1st classday0.5897.00448.50
0124LABMason 2nd classMason 2nd classday0.5816.00408.00
0114LABBeldarday3736.002,208.00
0115LABCoolieday3736.002,208.00
BUILD-UP TO RATE
TOTAL
20,264.73
Add 1 % Water charges on “W-A”
+156.10
TOTAL
20,420.83
Add GST on “X-A” (multiplying factor 0.2127)
+3,353.35
TOTAL
23,774.18
Add 15% CPOH on “Y-A”
+2,867.85
TOTAL
26,642.03
Add Cess @ 1% on “Z-A”
+219.87
Cost of one soak pit
26,861.90
SAY
₹26,861.90
D-02/SOURCEPRINTED PAGE 1774
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1774

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1774. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDRAINAGE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.