Providing and laying cement concrete 1:5:10 (1 cement : 5 coarse sand : 10 graded stone aggregate 40 mm nominal size) up to haunches of S.W. pipes including bed concrete as per standard design
- Item number
- 19.3.5
- Analysis basis
- 10 metre
- Priced inputs
- 1
- Derived rate
- ₹1,173.35/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.3.5 (Providing and laying cement concrete 1:5:10 (1 cement : 5 coarse sand : 10 graded stone aggregate 40 mm nominal size) up to haunches of S.W. pipes including bed concrete as per standard design : 300 mm diameter S.W. pipe) is derived from 1 priced inputs for 10 metre and works out to ₹1,173.35 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- Area = WxD1 + 2x½xR Cot QxR [R²/2(3.14/2-Q)] - (3.14/2)R²
- = WD1 + R²(Cot Q) - R²(3.14/2 - Q)(3.14/2)R2
- = WD1 + R²(Cot Q - 3.14 + Q)
- Where Sin Q = [R/(W/2)] = 2R/W
- W = D + X ; X = 300 mm, D = 300 + 25 +
- 25 = 350 mm
- W = 350 + 300 = 650 mm
- D1 = Depth = 150 + (½ x 350) = 325 mm
- R = 175 mm
- Sin Q = (2x175)/650 = 0.5385 therefor Q
- = 32°34’
- Hence Tan Q = 0.6387
- Area = 650 x 325 + (175)² (Cot Q - 3.14
- + Q)
- = [211250 + 30625 (1/0.6387 - 180°+
- 32°34’)] sqmm
- = [211250 + 30625 (1.566 - 147°26’ x
- 3.14/180)] sqmm
- = [211250 + 30625 x (1.566-2.571)]
- sqmm
- = [211250 + 30625 x (-1.005)] sqmm
- = [211250 - 30778.13) sqmm
- = 180471.87 sqmm
- For 10 m length qty. of concrete reqd. =
- 0.180x10 = 1.80 cum
- Say 0.180 sqm
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per item no 4.1.10 of SH : Concrete WorkRate as per item 4.1.10 | cum | 1.8 | 6,518.60 | 11,733.48 |
- Cost of 10 metre
- 11,733.48
- Cost per metre
- 1,173.35
- SAY
- ₹1,173.35
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1698
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1698. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.