Skip to main content

CPWD Analysis of Rates · Drainage

Providing and fixing square-mouth S.W. gully trap class SP-1 complete with C.I. grating brick masonry chamber with water tight C.I. cover with frame of 300 x300 mm size (inside) the weight of cover to be not less than 4.50 kg and frame to be not less than 2.70 kg as per standard design: 100x100 mm size P type

With common burnt clay F.P.S. (non modular) bricks of class designation 7.5

Item number
19.4.1.1
Analysis basis
Details of cost of one gully tarp
Priced inputs
8
Derived rate
2,707.65

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.4.1.1 Providing and fixing square-mouth S.W. gully trap class SP-1 complete with C.I. grating brick masonry chamber with water tight C.I. cover with frame of 300 x300 mm size (inside) the weight of cover to be not less than 4.50 kg and frame to be not less than 2.70 kg as per standard design: 100x100 mm size P type With common burnt clay F.P.S. (non modular) bricks of class designation 7.5 — is derived from 8 priced inputs and works out to ₹2,707.65 after water charges, GST, CPOH and cess. The full build-up is below.

  • Cement concrete 1:5:10 ( 1 cement : 5
  • fine sand : 10 graded stone aggregate 40
  • mm nominal size)
  • 0.68x0.68x0.10 m = 0.046 cum
  • Concrete around trap
  • 0.30x0.30x0.675 m = 0.061 cum
  • Total=0.107 cum
  • 0.345÷3x[0.09+0.01+(0.09x0.01)1/2] =
  • 0.015 cum
  • 3.14/4x(0.124)²x0.47 = 0.006 cum
  • Total= 0.021 cum
  • Net quantity 0.107 cum (-) 0.021 cum =
  • 0.086 cum say 0.09 cum
  • Brick work with 7.5 class designation
  • brick in cement mortar 1:4 (1 cement : 4
  • coarse sand)
  • 1.66x0.115x0.675 m = 0.129 cum. say
  • 0.13 cum
  • Cement concrete 1:2:4 ( 1 cement : 2
  • coarse sand : 4 graded stone aggregate
  • 20 mm nominal size)
  • 1.66x0.115x0.04 m = 0.008 cum
  • 12 mm cement plaster 1:3 (1 cement : 3
  • coarse sand) finished with floating coat of
  • neat cement :
  • [1/2x0.358x(1.20+0.40)] = 0.286 sqm.
  • Deduct:
  • say 0.29 sqm
CodeInputUnitQuantityRate (INR)Amount (INR)
1900S.W. gully trap P type 100x100 mmMaterialeach1127.00127.00
1364C.I. grating 100x100 mmMaterialeach140.0040.00
1352C.I. cover and frame 300x300 mm insideMaterialeach1525.00525.00
9977Carriage of materialsMaterialL.S.4.52.2710.22
Rate as per item no 4.1.11 of SH : Concrete WorkRate as per item 4.1.11Sub-analysiscum0.096,189.65557.07
Rate as per item no 6.1.1 of SH : Brick WorkRate as per item 6.1.1Sub-analysiscum0.137,370.65958.18
Rate as per item no 4.1.3 of SH : Concrete WorkRate as per item 4.1.3Sub-analysiscum0.0087,878.5063.03
Rate as per item no 13.9.1 of SH : FinishingRate as per item 13.9.1Sub-analysissqm0.29449.55130.37
TOTAL
2,410.87
Add 1 % Water charges on “W-A”
7.02
TOTAL
2,417.89
Add GST on “X-A” (multiplying factor 0.2127)
150.86
TOTAL
2,568.75
Add 15% CPOH on “Y-A”
129.02
TOTAL
2,697.77
Add Cess @ 1% on “Z-A”
9.89
Cost of each
2,707.66
Say
2,707.65

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1698. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works