CPWD Analysis of Rates · Drainage

Providing and laying cement concrete 1:5:10 (1 cement : 5 coarse sand : 10 graded stone aggregate 40 mm nominal size) up to haunches of S.W. pipes including bed concrete as per standard design

250 mm diameter S.W. pipe

Item number
19.3.4
Analysis basis
Details of cost for 10 metre length pipe
Priced inputs
1
Derived rate
1,016.90 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.3.4 Providing and laying cement concrete 1:5:10 (1 cement : 5 coarse sand : 10 graded stone aggregate 40 mm nominal size) up to haunches of S.W. pipes including bed concrete as per standard design : 250 mm diameter S.W. pipe — is derived from 1 priced inputs for 10 metre and works out to ₹1,016.90 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • Area = WxD1 + 2x½xR Cot QxR [R²/2(3.14/2-Q)] - (3.14/2)R²
  • = WD1 + R²(Cot Q) - R²(3.14/2 - Q)(3.14/2)R2
  • = WD1 + R²(Cot Q - 3.14 + Q)
  • Where Sin Q = [R/(W/2)] = 2R/W
  • W = D + X ; X = 300 mm, D = 250 + 20 +
  • 20 = 290 mm
  • W = 290 + 300 = 590 mm
  • D1 = Depth = 150 + (½ x 290) = 295 mm
  • R = 145 mm
  • Sin Q = (2x145)/590 = 0.49154
  • therefor Q = 29°26’
  • Hence Tan Q = 0.5635
  • Area = 590 x 295 + (145)² (Cot Q - 3.14 + Q)
  • = [174050 + 21025 (1/0.5635 - 180°+
  • 29°26’)] sqmm
  • = [174050 + 21025 (1.77 - 150°34’ x
  • 3.14/180)] sqmm
  • = [174050 + 21025 x (1.77-2.63)] sqmm
  • = [174050 + 21025 x (-0.86)] sqmm
  • = (174050 - 18081.5) sqmm
  • = 155968.5 sqmm
  • For 10 m length qty. of concrete reqd. =
  • 0.156x10 = 1.56 cum
  • Say 155968 sqmm or 0.156 sqm
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per item no 4.1.10 of SH : Concrete WorkRate as per item 4.1.10Sub-analysiscum1.566,518.6010,169.02
Cost of 10 metre
10,169.02
Cost per metre
1,016.90
Say
1,016.90

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1697. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.