Providing and laying cement concrete 1:5:10 (1 cement : 5 coarse sand : 10 graded stone aggregate 40 mm nominal size) up to haunches of S.W. pipes including bed concrete as per standard design
- Item number
- 19.3.3
- Analysis basis
- 10 metre
- Priced inputs
- 1
- Derived rate
- ₹873.50/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.3.3 (Providing and laying cement concrete 1:5:10 (1 cement : 5 coarse sand : 10 graded stone aggregate 40 mm nominal size) up to haunches of S.W. pipes including bed concrete as per standard design : 200 mm diameter S.W. pipe) is derived from 1 priced inputs for 10 metre and works out to ₹873.50 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- Area = WxD1 + 2x½xR Cot QxR [R²/2(3.14/2-Q)] - (3.14/2)R²
- = WD1 + R²(Cot Q) - R²(3.14/2 - Q) (3.14/2)R2
- = WD1 + R²(Cot Q - 3.14 + Q)
- Where Sin Q = [R/(W/2)] = 2R/W
- W = D + X ; X = 300 mm, D = 200+ 17 +
- 17 = 234 mm
- W = 234 + 300 = 534 mm
- D1 = Depth = 150 + (½ x 234) = 267 mm
- R = 117 mm
- Sin Q = (2x117)/534 = 0.4382 therefor
- Q= 26°0’
- Hence Tan Q = 0.4877
- Area = 534 x 267 + (117)² (Cot Q - 3.14
- + Q)
- = [142578 + 13689 (1/0.4877 - 180°+
- 26°0’)] sqmm
- = [142578 + 13689 (2.05 - 154°0’ x
- 3.14/180)] sqmm
- = [142578 + 13689 x (2.05-2.69)] sqmm
- = [142578 + 13689 x (-0.64)] sqmm
- = (142578 - 8760.96) sqmm
- = 133817.04 sqmm
- For 10 m length qty. of concrete reqd. =
- 0.134x10 = 1.34 cum
- Say 133817 sqmm or 0.134 sqm
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per item no 4.1.10 of SH : Concrete WorkRate as per item 4.1.10 | cum | 1.34 | 6,518.60 | 8,734.92 |
- Cost of 10 metre
- 8,734.92
- Cost per metre
- 873.49
- SAY
- ₹873.50
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1696
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1696. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.