CPWD Analysis of Rates · Drainage

Providing and laying cement concrete 1:5:10 (1 cement : 5 coarse sand : 10 graded stone aggregate 40 mm nominal size) up to haunches of S.W. pipes including bed concrete as per standard design

150 mm diameter S.W. pipe

Item number
19.3.2
Analysis basis
Details of cost for 10 metre length pipe
Priced inputs
1
Derived rate
743.10 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.3.2 Providing and laying cement concrete 1:5:10 (1 cement : 5 coarse sand : 10 graded stone aggregate 40 mm nominal size) up to haunches of S.W. pipes including bed concrete as per standard design : 150 mm diameter S.W. pipe — is derived from 1 priced inputs for 10 metre and works out to ₹743.10 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • Area = WxD1 + 2x½xR Cot QxR [R²/2(3.14/2-Q)] - (3.14/2)R²
  • = WD1 + R²(Cot Q) - R²(3.14/2 - Q)(3.14/2)R²
  • = WD1 + R²(Cot Q - 3.14 + Q)
  • Where Sin Q = [R/(W/2)] = 2R/W
  • W = D + X ; X = 300 mm, D = 150 + 16+
  • 16 = 182 mm
  • W = 182 + 300 = 482 mm
  • D1 = Depth = 150 + (½ x 182) = 241 mm
  • R = 91 mm
  • Sin Q = (2x91)/482 = 0.3776 therefor Q
  • = 22°12’
  • Hence Tan Q = 0.4081
  • Area = 482 x 241 + (91)² (Cot Q - 3.14 +
  • Q)
  • = [116162 + 8281 (1/0.4081 - 180°+
  • 22°12’)] sqmm
  • = [116162 + 8281 (2.45 - 157°48’
  • x3.14/180)] sqmm
  • = [116162 + 8281 x (2.45-2.75)] sqmm
  • = [116162 + 8281 x (-0.30)] sqmm
  • = (116162 - 2484.3) sqmm = 113677.7
  • sqmm
  • For 10 m length qty. of concrete reqd.
  • = 0.1136777x10 = 1.136777 cum. Say
  • 1.14 cum
  • Say 113677.7 sqmm or 0.1136777 sqm
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per item no 4.1.10 of SH : Concrete WorkRate as per item 4.1.10Sub-analysiscum1.146,518.607,431.20
Cost of 10 metre
7,431.20
Cost per metre
743.12
Say
743.10

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1696. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.