Providing and laying cement concrete 1:5:10 (1 cement : 5 coarse sand : 10 graded stone aggregate 40 mm nominal size) up to haunches of S.W. pipes including bed concrete as per standard design

100 mm diameter S.W. pipe

Item number
19.3.1
Analysis basis
Detail of cost for 100 metre
Priced inputs
1
Derived rate
458.50 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.3.1 Providing and laying cement concrete 1:5:10 (1 cement : 5 coarse sand : 10 graded stone aggregate 40 mm nominal size) up to haunches of S.W. pipes including bed concrete as per standard design : 100 mm diameter S.W. pipe — is derived from 1 priced inputs for 100 metre and works out to ₹458.50 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • Area = WxD1 + 2x½xR Cot QxR [R²/2(3.14/2-Q)] - (3.14/2)R²
  • = WD1 + R²(Cot Q) - R²(3.14/2 - Q)
  • -(3.14/2)R²
  • = WD1+R²(cot Q-3.14 + Q)
  • Where Sin Q = [R/(W/2)] = 2R/W
  • W = D + X ; X = 300 mm, D = 100 + 12
  • +12 = 124 mm
  • W = 124 + 300 = 424 mm
  • D1 = Depth = 100 + (½ x 124) = 162 mm
  • R = 62 mm
  • Sin Q = (2x62)/424 = 0.292 therefor Q =
  • 17°0’
  • Hence Tan Q = 0.3057
  • Area = 424 x 162 + (62)² (Cot Q - 3.14 +
  • Q)
  • = [68688 + 3844 (1/0.3057 - 180° +
  • 17°0’)] sqmm
  • = [68688 + 3844 (3.27 - 163°0’ x
  • 3.14/180)] sqmm
  • = (68688 + 3844 x 0.43) sqmm
  • = (68688 + 1652.92) sqmm
  • = 70340.92 sqmm
  • For 100 m length qty. of concrete reqd. =
  • 0.07034x100 = 7.034 cum
  • Say 70341 sqmm or 0.07034 sqm
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per item no 4.1.10 of SH : Concrete WorkRate as per item 4.1.10Sub-analysiscum7.0346,518.6045,851.83
Cost of 100 metre
45,851.83
Cost per metre
458.52
Say
458.50

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1695. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.