CPWD Analysis of Rates · Drainage

Constructing brick masonry road gully chamber 45x45x77.5 cm with bricks in cement mortar

1:4 (1 cement : 4 coarse sand ) with precast R.C.C. vertical grating complete as per standard design : With common burnt clay F.P.S. (non modular) bricks of class designation 7.5

Item number
19.28.1
Analysis basis
Details of cost for one chamber
Priced inputs
9
Derived rate
6,889.80 / one chamber

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.28.1 Constructing brick masonry road gully chamber 45x45x77.5 cm with bricks in cement mortar 1:4 (1 cement : 4 coarse sand ) with precast R.C.C. vertical grating complete as per standard design : With common burnt clay F.P.S. (non modular) bricks of class designation 7.5 — is derived from 9 priced inputs for one chamber and works out to ₹6,889.80 per one chamber after water charges, GST, CPOH and cess. The full build-up is below.

  • Cement concrete 1:5:10 (1 cement : 5
  • fine sand : 10 graded stone aggregate 40
  • mm nominal size)
  • 1.06mx1.06mx0.15 m= 0.17 cum
  • Brick work in bricks of class designation
  • 7.5 in cement mortar 1:4 ( 1 cement : 4
  • coarse sand)
  • 2.72 m x 0.23m x0.70 m = 0.438 cum
  • cum
  • Block 3x(0.075)³ = 0.001 cum
  • Total deduction = 0.011 cum
  • Net qty. = 0.438 (-) 0.011 = 0.427 cum
  • 12 mm cement plaster 1:3 ( 1 cement : 3
  • coarse sand) finished with floating coat of
  • neat cement
  • Wall : 1.80x0.70 m = 1.26 sqm
  • Bed : 0.45x0.45 m = 0.202 sqm
  • Top : 0.45x0.20 m = 0.09 sqm
  • Sides : 2x0.20x0.10 m = 0.04 sqm
  • Total= 1.592 sqm
  • 0.45x0.10 m = 0.045 sqm
  • Net qty. = 1.592 (-) 0.045 = 1.547 cum
  • Cement concrete 1:2:4 ( 1 cement : 2
  • coarse sand : 4 graded stone aggregate
  • 20 mm nominal size)
  • Block = 3x(0.75)³ = 0.001 cum
  • R.C.C. 1:1.5:3 (1 cement : 1.5 coarse
  • sand : 3 graded stone aggregate 20 mm
  • nominal size)
  • 0.91x0.91x0.075 m = 0.062 cum Say
  • 0.06 cum
  • Form work
  • 0.45x0.45 m = 0.202 sqm
  • 0.45x0.20 m = 0.09 sqm
  • outside slab : 3.40x0.075 m = 0.255 sqm
  • Total= 0.547 sqm Say 0.55 sqm
  • T.M.T. bars steel reinforcement for R.C.C
  • work
  • 0.062 cum @ 80 kg/cum = 4.96 kg
  • Deduct opening 0.45x0.23x0.10 m = 0.01
  • Say 0.43 cum
  • Deduct opening
  • Say 1.55 cum
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per item no 4.1.11 of SH : Concrete WorkRate as per item 4.1.11Sub-analysiscum0.176,189.651,052.24
Rate as per item no 6.1.1 of SH : Brick WorkRate as per item 6.1.1Sub-analysiscum0.437,370.653,169.38
Rate as per item no 13.9.1 of SH : FinishingRate as per item 13.9.1Sub-analysissqm1.55449.55696.80
Rate as per item no 4.1.3 of SH : Concrete WorkRate as per item 4.1.3Sub-analysiscum0.0017,878.507.88
Rate as per item no. 5.1.2 of SH : RCC workRate as per item 5.1.2Sub-analysiscum0.069,045.75542.75
Rate as per item no 5.9.2 of SH : RCCRate as per item 5.9.2Sub-analysissqm0.55842.50463.38
Rate as per item no. 5.22.6 of SH : RCC workRate as per item 5.22.6Sub-analysiskg4.96107.85534.94
7381Precast R.C.C. grating with frame 450x100 mm vertical gratingMaterialeach1250.00250.00
9999Fixing and carriage of R.C.C. gratingMaterialL.S.20.672.2746.92
TOTAL
6,764.29
Add 1 % Water charges on “W-A”
2.97
TOTAL
6,767.26
Add GST on “X-A” (multiplying factor 0.2127)
63.79
TOTAL
6,831.05
Add 15% CPOH on “Y-A”
54.55
TOTAL
6,885.60
Add Cess @ 1% on “Z-A”
4.18
Cost of one chamber
6,889.78
Say
6,889.80

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1766. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.