Constructing brick masonry road gully chamber 50x45x60 cm with bricks in cement mortar

1:4 (1 cement : 4 coarse sand) including 500x450 mm pre-cast R.C.C. horizontal grating with frame complete as per standard design : With common burnt clay F.P.S. (non modular) bricks of class designation 7.5
Item number
19.27.1
Analysis basis
one chamber
Priced inputs
8
Derived rate
₹5,957.90/ ONE CHAMBER
D-01/RATE ANALYSISITEM 19.27.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.27.1 (Constructing brick masonry road gully chamber 50x45x60 cm with bricks in cement mortar 1:4 (1 cement : 4 coarse sand) including 500x450 mm pre-cast R.C.C. horizontal grating with frame complete as per standard design : With common burnt clay F.P.S. (non modular) bricks of class designation 7.5) is derived from 8 priced inputs for one chamber and works out to ₹5,957.90 per one chamber after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement concrete 1:5:10 (1 cement : 5
  • fine sand : 10 graded stone aggregate 40
  • mm nominal size)
  • 1.11mx1.06mx0.15 m= 0.176 cum Say
  • 0.18 cum
  • Brick work in bricks of class designation
  • 7.5 in cement mortar 1:4 ( 1 cement : 4
  • coarse sand)
  • 2.82 m x 0.23m x0.45 m = 0.29 cum
  • 12 mm cement plaster 1:3 ( 1 cement : 3
  • coarse sand) finished with floating coat of
  • neat cement
  • Wall : 1.90x0.45 m = 0.855 sqm
  • Bed : 0.45x0.50 m = 0.225 sqm
  • Total= 1.080 sqm
  • Cement concrete 1:2:4 ( 1 cement : 2
  • coarse sand : 4 graded stone aggregate
  • 20 mm nominal size)
  • 2.82x0.23x0.15 m = 0.097 cum Say 0.10
  • cum
  • Form work
  • 3.50x0.15 m = 0.525 sqm Say 0.53 sqm
ANALYSIS OF RATES · ITEM 19.27.1DETAILS OF COST FOR ONE CHAMBER
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per item no 4.1.11 of SH : Concrete WorkRate as per item 4.1.11cum0.186,189.651,114.14
SUBRate as per item no 6.1.1 of SH : Brick WorkRate as per item 6.1.1cum0.297,370.652,137.49
SUBRate as per item no 13.9.1 of SH : FinishingRate as per item 13.9.1sqm1.08449.55485.51
SUBRate as per item no 4.1.3 of SH : Concrete WorkRate as per item 4.1.3cum0.17,878.50787.85
SUBRate as per item no 5.9.2 of SH : RCCRate as per item 5.9.2sqm0.53842.50446.53
7380MATPrecast R.C.C. grating with frame 500x450 mm horizontal gratingeach1665.00665.00
9977MATCarriage of R.C.C. gratingL.S.7.152.2716.23
9999MATFixing R.C.C. gratingL.S.5.332.2712.10
BUILD-UP TO RATE
TOTAL
5,664.85
Add 1 % Water charges on “W-A”
+6.93
TOTAL
5,671.78
Add GST on “X-A” (multiplying factor 0.2127)
+148.95
TOTAL
5,820.73
Add 15% CPOH on “Y-A”
+127.38
TOTAL
5,948.11
Add Cess @ 1% on “Z-A”
+9.77
Cost of one chamber
5,957.88
SAY
₹5,957.90
D-02/SOURCEPRINTED PAGE 1765
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1765

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1765. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDRAINAGE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.