CPWD Analysis of Rates · Drainage
Constructing brick masonry road gully chamber 50x45x60 cm with bricks in cement mortar
1:4 (1 cement : 4 coarse sand) including 500x450 mm pre-cast R.C.C. horizontal grating with frame complete as per standard design : With common burnt clay F.P.S. (non modular) bricks of class designation 7.5
- Item number
- 19.27.1
- Analysis basis
- Details of cost for one chamber
- Priced inputs
- 8
- Derived rate
- ₹5,957.90 / one chamber
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.27.1 — Constructing brick masonry road gully chamber 50x45x60 cm with bricks in cement mortar 1:4 (1 cement : 4 coarse sand) including 500x450 mm pre-cast R.C.C. horizontal grating with frame complete as per standard design : With common burnt clay F.P.S. (non modular) bricks of class designation 7.5 — is derived from 8 priced inputs for one chamber and works out to ₹5,957.90 per one chamber after water charges, GST, CPOH and cess. The full build-up is below.
- Cement concrete 1:5:10 (1 cement : 5
- fine sand : 10 graded stone aggregate 40
- mm nominal size)
- 1.11mx1.06mx0.15 m= 0.176 cum Say
- 0.18 cum
- Brick work in bricks of class designation
- 7.5 in cement mortar 1:4 ( 1 cement : 4
- coarse sand)
- 2.82 m x 0.23m x0.45 m = 0.29 cum
- 12 mm cement plaster 1:3 ( 1 cement : 3
- coarse sand) finished with floating coat of
- neat cement
- Wall : 1.90x0.45 m = 0.855 sqm
- Bed : 0.45x0.50 m = 0.225 sqm
- Total= 1.080 sqm
- Cement concrete 1:2:4 ( 1 cement : 2
- coarse sand : 4 graded stone aggregate
- 20 mm nominal size)
- 2.82x0.23x0.15 m = 0.097 cum Say 0.10
- cum
- Form work
- 3.50x0.15 m = 0.525 sqm Say 0.53 sqm
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| Rate as per item no 4.1.11 of SH : Concrete WorkRate as per item 4.1.11Sub-analysis | cum | 0.18 | 6,189.65 | 1,114.14 | |
| Rate as per item no 6.1.1 of SH : Brick WorkRate as per item 6.1.1Sub-analysis | cum | 0.29 | 7,370.65 | 2,137.49 | |
| Rate as per item no 13.9.1 of SH : FinishingRate as per item 13.9.1Sub-analysis | sqm | 1.08 | 449.55 | 485.51 | |
| Rate as per item no 4.1.3 of SH : Concrete WorkRate as per item 4.1.3Sub-analysis | cum | 0.1 | 7,878.50 | 787.85 | |
| Rate as per item no 5.9.2 of SH : RCCRate as per item 5.9.2Sub-analysis | sqm | 0.53 | 842.50 | 446.53 | |
| 7380 | Precast R.C.C. grating with frame 500x450 mm horizontal gratingMaterial | each | 1 | 665.00 | 665.00 |
| 9977 | Carriage of R.C.C. gratingMaterial | L.S. | 7.15 | 2.27 | 16.23 |
| 9999 | Fixing R.C.C. gratingMaterial | L.S. | 5.33 | 2.27 | 12.10 |
- TOTAL
- 5,664.85
- Add 1 % Water charges on “W-A”
- 6.93
- TOTAL
- 5,671.78
- Add GST on “X-A” (multiplying factor 0.2127)
- 148.95
- TOTAL
- 5,820.73
- Add 15% CPOH on “Y-A”
- 127.38
- TOTAL
- 5,948.11
- Add Cess @ 1% on “Z-A”
- 9.77
- Cost of one chamber
- 5,957.88
- Say
- 5,957.90
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1765. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works