Constructing brick masonry road gully chamber 50x45x60 cm with bricks in cement mortar
- Item number
- 19.27.1
- Analysis basis
- one chamber
- Priced inputs
- 8
- Derived rate
- ₹5,957.90/ ONE CHAMBER
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.27.1 (Constructing brick masonry road gully chamber 50x45x60 cm with bricks in cement mortar 1:4 (1 cement : 4 coarse sand) including 500x450 mm pre-cast R.C.C. horizontal grating with frame complete as per standard design : With common burnt clay F.P.S. (non modular) bricks of class designation 7.5) is derived from 8 priced inputs for one chamber and works out to ₹5,957.90 per one chamber after water charges, GST, CPOH and cess. The full build-up is below.
- Cement concrete 1:5:10 (1 cement : 5
- fine sand : 10 graded stone aggregate 40
- mm nominal size)
- 1.11mx1.06mx0.15 m= 0.176 cum Say
- 0.18 cum
- Brick work in bricks of class designation
- 7.5 in cement mortar 1:4 ( 1 cement : 4
- coarse sand)
- 2.82 m x 0.23m x0.45 m = 0.29 cum
- 12 mm cement plaster 1:3 ( 1 cement : 3
- coarse sand) finished with floating coat of
- neat cement
- Wall : 1.90x0.45 m = 0.855 sqm
- Bed : 0.45x0.50 m = 0.225 sqm
- Total= 1.080 sqm
- Cement concrete 1:2:4 ( 1 cement : 2
- coarse sand : 4 graded stone aggregate
- 20 mm nominal size)
- 2.82x0.23x0.15 m = 0.097 cum Say 0.10
- cum
- Form work
- 3.50x0.15 m = 0.525 sqm Say 0.53 sqm
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per item no 4.1.11 of SH : Concrete WorkRate as per item 4.1.11 | cum | 0.18 | 6,189.65 | 1,114.14 | |
| SUB | Rate as per item no 6.1.1 of SH : Brick WorkRate as per item 6.1.1 | cum | 0.29 | 7,370.65 | 2,137.49 | |
| SUB | Rate as per item no 13.9.1 of SH : FinishingRate as per item 13.9.1 | sqm | 1.08 | 449.55 | 485.51 | |
| SUB | Rate as per item no 4.1.3 of SH : Concrete WorkRate as per item 4.1.3 | cum | 0.1 | 7,878.50 | 787.85 | |
| SUB | Rate as per item no 5.9.2 of SH : RCCRate as per item 5.9.2 | sqm | 0.53 | 842.50 | 446.53 | |
| 7380 | MAT | Precast R.C.C. grating with frame 500x450 mm horizontal grating | each | 1 | 665.00 | 665.00 |
| 9977 | MAT | Carriage of R.C.C. grating | L.S. | 7.15 | 2.27 | 16.23 |
| 9999 | MAT | Fixing R.C.C. grating | L.S. | 5.33 | 2.27 | 12.10 |
- TOTAL
- 5,664.85
- Add 1 % Water charges on “W-A”
- +6.93
- TOTAL
- 5,671.78
- Add GST on “X-A” (multiplying factor 0.2127)
- +148.95
- TOTAL
- 5,820.73
- Add 15% CPOH on “Y-A”
- +127.38
- TOTAL
- 5,948.11
- Add Cess @ 1% on “Z-A”
- +9.77
- Cost of one chamber
- 5,957.88
- SAY
- ₹5,957.90
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1765
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1765. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.