CPWD Analysis of Rates · Drainage
Constructing brick masonry road gully chamber 110x50x77.5 cm with bricks in cement mortar
1:4 (1 cement : 4 coarse sand) including 500x450 mm precast R.C.C. horizontal grating with frame and vertical grating complete as per standard design : With common burnt clay F.P.S. (non modular) bricks of class designation 7.5
- Item number
- 19.29.1
- Analysis basis
- Details of cost for one chamber
- Priced inputs
- 13
- Derived rate
- ₹11,520.55 / one chamber
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.29.1 — Constructing brick masonry road gully chamber 110x50x77.5 cm with bricks in cement mortar 1:4 (1 cement : 4 coarse sand) including 500x450 mm precast R.C.C. horizontal grating with frame and vertical grating complete as per standard design : With common burnt clay F.P.S. (non modular) bricks of class designation 7.5 — is derived from 13 priced inputs for one chamber and works out to ₹11,520.55 per one chamber after water charges, GST, CPOH and cess. The full build-up is below.
- Cement concrete 1:5:10 (1 cement : 5
- fine sand : 10 graded stone aggregate 40
- mm nominal size)
- 1.71mx1.11mx0.15 m = 0.285 cum Say
- 0.29 cum
- Brick work in bricks of class designation
- 7.5 in cement mortar 1:4 ( 1 cement : 4
- coarse sand)
- 1.86 m x 0.23m x0.45 m = 0.193 cum
- 2.26mx0.23mx0.70 m = 0.364 cum
- Total= 0.557 cum
- 2x0.23x0.20x0.20 m = (-) 0.018 cum
- Nte Qty= 0.0539 cum Say 0.54 cum
- 12 mm cement plaster 1:3 ( 1 cement : 3
- coarse sand) finished with floating coat of
- neat cement
- Wall : 1.80x0.70 m = 1.26 sqm
- Wall : 1.40x0.45 m = 0.63 sqm
- Bed : 1.10x0.50 m = 0.55 sqm
- Total= 2.44 sqm
- Net Qty= 2.36 sqm
- Cement concrete 1:2:4 ( 1 cement : 2
- coarse sand : 4 graded stone aggregate
- 20 mm nominal size)
- Block = 1.92x0.23x0.15 = 0.07 cum
- R.C.C. 1:1.5:3 (1 cement : 1.5 coarse
- sand : 3 graded stone aggregate 20 mm
- nominal size)
- 0.88x0.96x0.075 m = 0.063 cum Say
- 0.06 cum
- R.C.C. 1:1.5:3 (1 cement: 1.5 coarse
- sand : 3 graded stone aggregate 20 mm
- nominal size) in lintels 1x0.96x0.20x0.20
- m = 0.04 cum
- upto floor five level
- Form work
- Slab bottom 0.50x0.65 m = 0.325 sqm
- Outer periphery 3.50x0.075 m = 0.263
- sqm
- 2.20x0.15 m = 0.330 sqm
- = 0.918 sqm Say 0.91 sqm
- T.M.T. bars steel reinforcement for R.C.C
- work
- (0.06+0.04) = 0.10 cum @ 80 kg/cum =
- 8.00 kg
- Deduct lintel portion
- Deduct 2x0.20x0.20 m = (-) 0.08 sqm
- Less labour for not lifting the materilas
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| Rate as per item no 4.1.11 of SH : Concrete WorkRate as per item 4.1.11Sub-analysis | cum | 0.29 | 6,189.65 | 1,795.00 | |
| Rate as per item no 6.1.1 of SH : Brick WorkRate as per item 6.1.1Sub-analysis | cum | 0.54 | 7,370.65 | 3,980.15 | |
| Rate as per item no 13.9.1 of SH : FinishingRate as per item 13.9.1Sub-analysis | sqm | 2.36 | 449.55 | 1,060.94 | |
| Rate as per item no 4.1.3 of SH : Concrete WorkRate as per item 4.1.3Sub-analysis | cum | 0.07 | 7,878.50 | 551.50 | |
| Rate as per item no. 5.1.2 of SH : RCC workRate as per item 5.1.2Sub-analysis | cum | 0.06 | 9,045.75 | 542.75 | |
| Rate as per item no. 5.13 of SH : RCC workRate as per item 5.13Sub-analysis | cum | 0.04 | 14,325.95 | 573.04 | |
| 0115 | Coolie (0.04x0.75x1.50=0.045 same as in item no 5.13)CoolieLabour | day | -0.045 | 736.00 | -33.12 |
| Rate as per item no 5.9.2 of SH : RCCRate as per item 5.9.2Sub-analysis | sqm | 0.91 | 842.50 | 766.68 | |
| Rate as per item no. 5.22.6 of SH : RCC workRate as per item 5.22.6Sub-analysis | kg | 8 | 107.85 | 862.80 | |
| 7380 | Precast R.C.C. grating with frame 500x450 mm horizontal gratingMaterial | each | 1 | 665.00 | 665.00 |
| 9977 | Carriage of R.C.C. gratingMaterial | L.S. | 7.15 | 2.27 | 16.23 |
| 7381 | Precast R.C.C. grating with frame 450x100 mm vertical gratingMaterial | each | 1 | 250.00 | 250.00 |
| 9999 | Labour for fixing precast R.C.C. grating and frameMaterial | L.S. | 34.06 | 2.27 | 77.32 |
- TOTAL
- 11,108.29
- Add 1 % Water charges on “W-A”
- 9.75
- TOTAL
- 11,118.04
- Add GST on “X-A” (multiplying factor 0.2127)
- 209.55
- TOTAL
- 11,327.59
- Add 15% CPOH on “Y-A”
- 179.21
- TOTAL
- 11,506.80
- Add Cess @ 1% on “Z-A”
- 13.74
- Cost of one chamber
- 11,520.54
- Say
- 11,520.55
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1767. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.