Constructing brick masonry road gully chamber 110x50x77.5 cm with bricks in cement mortar

1:4 (1 cement : 4 coarse sand) including 500x450 mm precast R.C.C. horizontal grating with frame and vertical grating complete as per standard design : With common burnt clay F.P.S. (non modular) bricks of class designation 7.5
Item number
19.29.1
Analysis basis
one chamber
Priced inputs
13
Derived rate
₹11,520.55/ ONE CHAMBER
D-01/RATE ANALYSISITEM 19.29.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.29.1 (Constructing brick masonry road gully chamber 110x50x77.5 cm with bricks in cement mortar 1:4 (1 cement : 4 coarse sand) including 500x450 mm precast R.C.C. horizontal grating with frame and vertical grating complete as per standard design : With common burnt clay F.P.S. (non modular) bricks of class designation 7.5) is derived from 13 priced inputs for one chamber and works out to ₹11,520.55 per one chamber after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement concrete 1:5:10 (1 cement : 5
  • fine sand : 10 graded stone aggregate 40
  • mm nominal size)
  • 1.71mx1.11mx0.15 m = 0.285 cum Say
  • 0.29 cum
  • Brick work in bricks of class designation
  • 7.5 in cement mortar 1:4 ( 1 cement : 4
  • coarse sand)
  • 1.86 m x 0.23m x0.45 m = 0.193 cum
  • 2.26mx0.23mx0.70 m = 0.364 cum
  • Total= 0.557 cum
  • 2x0.23x0.20x0.20 m = (-) 0.018 cum
  • Nte Qty= 0.0539 cum Say 0.54 cum
  • 12 mm cement plaster 1:3 ( 1 cement : 3
  • coarse sand) finished with floating coat of
  • neat cement
  • Wall : 1.80x0.70 m = 1.26 sqm
  • Wall : 1.40x0.45 m = 0.63 sqm
  • Bed : 1.10x0.50 m = 0.55 sqm
  • Total= 2.44 sqm
  • Net Qty= 2.36 sqm
  • Cement concrete 1:2:4 ( 1 cement : 2
  • coarse sand : 4 graded stone aggregate
  • 20 mm nominal size)
  • Block = 1.92x0.23x0.15 = 0.07 cum
  • R.C.C. 1:1.5:3 (1 cement : 1.5 coarse
  • sand : 3 graded stone aggregate 20 mm
  • nominal size)
  • 0.88x0.96x0.075 m = 0.063 cum Say
  • 0.06 cum
  • R.C.C. 1:1.5:3 (1 cement: 1.5 coarse
  • sand : 3 graded stone aggregate 20 mm
  • nominal size) in lintels 1x0.96x0.20x0.20
  • m = 0.04 cum
  • upto floor five level
  • Form work
  • Slab bottom 0.50x0.65 m = 0.325 sqm
  • Outer periphery 3.50x0.075 m = 0.263
  • sqm
  • 2.20x0.15 m = 0.330 sqm
  • = 0.918 sqm Say 0.91 sqm
  • T.M.T. bars steel reinforcement for R.C.C
  • work
  • (0.06+0.04) = 0.10 cum @ 80 kg/cum =
  • 8.00 kg
  • Deduct lintel portion
  • Deduct 2x0.20x0.20 m = (-) 0.08 sqm
  • Less labour for not lifting the materilas
ANALYSIS OF RATES · ITEM 19.29.1DETAILS OF COST FOR ONE CHAMBER
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per item no 4.1.11 of SH : Concrete WorkRate as per item 4.1.11cum0.296,189.651,795.00
SUBRate as per item no 6.1.1 of SH : Brick WorkRate as per item 6.1.1cum0.547,370.653,980.15
SUBRate as per item no 13.9.1 of SH : FinishingRate as per item 13.9.1sqm2.36449.551,060.94
SUBRate as per item no 4.1.3 of SH : Concrete WorkRate as per item 4.1.3cum0.077,878.50551.50
SUBRate as per item no. 5.1.2 of SH : RCC workRate as per item 5.1.2cum0.069,045.75542.75
SUBRate as per item no. 5.13 of SH : RCC workRate as per item 5.13cum0.0414,325.95573.04
0115LABCoolie (0.04x0.75x1.50=0.045 same as in item no 5.13)Coolieday-0.045736.00-33.12
SUBRate as per item no 5.9.2 of SH : RCCRate as per item 5.9.2sqm0.91842.50766.68
SUBRate as per item no. 5.22.6 of SH : RCC workRate as per item 5.22.6kg8107.85862.80
7380MATPrecast R.C.C. grating with frame 500x450 mm horizontal gratingeach1665.00665.00
9977MATCarriage of R.C.C. gratingL.S.7.152.2716.23
7381MATPrecast R.C.C. grating with frame 450x100 mm vertical gratingeach1250.00250.00
9999MATLabour for fixing precast R.C.C. grating and frameL.S.34.062.2777.32
BUILD-UP TO RATE
TOTAL
11,108.29
Add 1 % Water charges on “W-A”
+9.75
TOTAL
11,118.04
Add GST on “X-A” (multiplying factor 0.2127)
+209.55
TOTAL
11,327.59
Add 15% CPOH on “Y-A”
+179.21
TOTAL
11,506.80
Add Cess @ 1% on “Z-A”
+13.74
Cost of one chamber
11,520.54
SAY
₹11,520.55
D-02/SOURCEPRINTED PAGE 1767
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1767

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1767. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.