Skip to main content

CPWD Analysis of Rates · Drainage

Raising manhole cover and frame slab to required level including dismantling existing slab and making good the damage as required (Raising depth of manhole to be paid separately)

Rectangular manhole 90x80 cm with rectangular cover 600 x 450 mm of grade LD - 2.5

Item number
19.26.1
Analysis basis
Details of cost for one manhole
Priced inputs
5
Derived rate
2,625.50 / one manhole

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.26.1 Raising manhole cover and frame slab to required level including dismantling existing slab and making good the damage as required (Raising depth of manhole to be paid separately) : Rectangular manhole 90x80 cm with rectangular cover 600 x 450 mm of grade LD - 2.5 — is derived from 5 priced inputs for one manhole and works out to ₹2,625.50 per one manhole after water charges, GST, CPOH and cess. The full build-up is below.

  • Dismantling of R.C.C slab of 1:1.5:3 (1
  • cement : 1.5 coarse sand (Zone - III): 3
  • aggregate stone 20 mm nominal size) =
  • 1.36x1.26x0.15 = 0.257 cum
  • 0.85x0.70x0.15 =(-) 0.089 cum
  • Net qty=0.168 cum Say 0.17 cum
  • Removal of R.C.C work 1:1.5:3 ( 1 cement : 1.5 coarse sand : 3 graded stone
  • aggregate 20 mm nominal size )
  • For raised slab = 1.36x1.26x0.15 = 0.257
  • cum
  • 0.85x0.70x0.15 =(-) 0.089 cum
  • Net qty = 0.168 cum Say 0.17 cum
  • Form work = 0.90x0.80 = 0.72 sqm
  • Net qty = 0.45 sqm
  • Less cover with frame portion
  • Less portion cover with frame =
  • Less cover = 0.60x0.45 =(-) 0.27 sqm
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per item no. 15.3 of SH : Dismantling and demolishingRate as per item 15.3Sub-analysiscum0.173,551.25603.71
9999Removal of R.C.C cover and frameMaterialL.S.7.152.2716.23
Rate as per item no. 5.1.2 of SH : RCC workRate as per item 5.1.2Sub-analysiscum0.179,045.751,537.78
Rate as per item no 5.9.3 of SH : RCC workRate as per item 5.9.3Sub-analysissqm0.45927.25417.26
9999SundriesMaterialL.S.13.522.2730.69
TOTAL
2,605.67
Add 1 % Water charges on “W-A”
0.47
TOTAL
2,606.14
Add GST on “X-A” (multiplying factor 0.2127)
10.08
TOTAL
2,616.22
Add 15% CPOH on “Y-A”
8.62
TOTAL
2,624.84
Add Cess @ 1% on “Z-A”
0.66
Cost of one no
2,625.50
Say
2,625.50

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1762. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works