Raising manhole cover and frame slab to required level including dismantling existing slab and making good the damage as required (Raising depth of manhole to be paid separately)

Rectangular manhole 120x90 cm with circular cover 500 mm dia of grade MD - 10
Item number
19.26.2
Analysis basis
one manhole
Priced inputs
5
Derived rate
₹4,168.05/ ONE MANHOLE
D-01/RATE ANALYSISITEM 19.26.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.26.2 (Raising manhole cover and frame slab to required level including dismantling existing slab and making good the damage as required (Raising depth of manhole to be paid separately) : Rectangular manhole 120x90 cm with circular cover 500 mm dia of grade MD - 10) is derived from 5 priced inputs for one manhole and works out to ₹4,168.05 per one manhole after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Dismantling of R.C.C slab of 1:1.5:3 (1
  • cement : 1.5 coarse sand : 3 aggregate
  • stone 20 mm nominal size)
  • 1.66x1.36x0.15 = 0.339 cum
  • 3.14/4x(0.80)²x0.15 =(-) 0.075 cum
  • Net qty 0.264 cum Say 0.26 cum
  • R.C.C work 1:1.5:3 ( 1 cement : 1.5
  • coarse sand : 3 graded stone aggregate
  • 20 mm nominal size )
  • 1.66x1.36x0.15 = 0.339 cum
  • 3.14/4x0.80x0.80x0.15 =(-) 0.075 cum
  • Net qty= 0.264 cum Say 0.26 cum
  • Form work = 1.2x0.90 = 1.08 sqm
  • sqm
  • Net qty= 0.884 sqm Say .88 sqm
  • Less for R.C.C cover with frame
  • Less portion cover with frame =
  • Less cover = 3.14/4x(0.50)² =(-) 0.196
ANALYSIS OF RATES · ITEM 19.26.2DETAILS OF COST FOR ONE MANHOLE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per item no. 15.3 of SH : Dismantling and demolishingRate as per item 15.3cum0.263,551.25923.33
9999MATRemoval of R.C.C cover and frameL.S.7.152.2716.23
SUBRate as per item no. 5.1.2 of SH : RCC workRate as per item 5.1.2cum0.269,045.752,351.90
SUBRate as per item no 5.9.3 of SH : RCC workRate as per item 5.9.3sqm0.88927.25815.98
9999MATSundriesL.S.16.642.2737.77
BUILD-UP TO RATE
TOTAL
4,145.21
Add 1 % Water charges on “W-A”
+0.54
TOTAL
4,145.75
Add GST on “X-A” (multiplying factor 0.2127)
+11.60
TOTAL
4,157.35
Add 15% CPOH on “Y-A”
+9.92
TOTAL
4,167.27
Add Cess @ 1% on “Z-A”
+0.76
Cost of one no
4,168.03
SAY
₹4,168.05
D-02/SOURCEPRINTED PAGE 1762
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1762

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1762. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDRAINAGE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.