CPWD Analysis of Rates · Drainage

Extra for depth of manholes dismantled

Circular manhole 122 cm diameter and beyond 1.68 m depth (up to 2.29 m depth)

Item number
19.25.4
Analysis basis
Details of cost for 0.61 metre
Priced inputs
6
Derived rate
2,229.20 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.25.4 Extra for depth of manholes dismantled : Circular manhole 122 cm diameter and beyond 1.68 m depth (up to 2.29 m depth) — is derived from 6 priced inputs for 0.61 metre and works out to ₹2,229.20 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • Dismantling cement concrete 1:3:6 (1
  • Cement : 3 coarse sand : 6 graded stone
  • aggregate 40mm nominal size)
  • 1.98x1.98x0.30 = 1.178 cum. Say 1.18
  • cum.
  • Dismantling IInd class brick work in
  • cement mortar 1:4 (1 Cement : 4 Coarse
  • sand)
  • Curved on plan
  • 3.14x1.45x0.85x0.23 = 0.891
  • 3.14x(1.45+0.79)/2x1.32x0.23 = 1.069
  • Total = 0.891 + 1.069 = 1.96 cum
  • Duduct arch ring and portion of pipe
  • 2x1/2x3.14x0.25mx0.23x0.10 m = 0.018
  • cum
  • 2x3.14/4x(0.15)²x0.23 = 0.008 cum
  • Total deduction = 0.026 cum
  • Net quantity 1.96-0.026 = 1.934 Say 1.93
  • cum
  • Qty in arch
  • 2x1/2x3.14x0.25 m x0.23x0.10 m
  • = 0.018 cum Say 0.02 cum
  • Total = 1.93 + 0.02 = 1.97 cum
  • Dismantling cemnet concrete 1:2:4 ( 1
  • cement : 2 coarse sand : 4 graded stone
  • aggregate 20 mm nominal size
  • For benching :
  • 3.14/4x(1.22)²x0.20 = 0.234 cum
  • [(2x8.133)/360]x(4/3)x3.14x(0.61)³
  • =0.043 cum
  • = 0.277 cum
  • 0.0216 cum
  • Net qty== 0.2554 cum Say 0.26 cum
  • For fixing cover : 3.14/4 x d2 x thickness
  • 0.7854x1.020x1.020x0.15 m =0.123 cum
  • (-)0.037 cum
  • Net qty= 0.086 cum Say 0.09 cum
  • Total = 0.26 + 0.09 = 0.35 cum
  • 1.68m deep
  • Less pipe :1.22x3.14/4x(0.15)²(-) =
  • Less cover 3.14/4x(0.28)² x 0.15 m : =
  • Deduct cost of dismantling manhole
CodeInputUnitQuantityRate (INR)Amount (INR)
(Rate as per item No.15.2.1 of SH. dismantling and Demolishing)Rate as per item 15.2.1Sub-analysiscum1.182,434.252,872.42
Rate as per item no 15.7.4 of SH : Dismantling and demolishingRate as per item 15.7.4Sub-analysiscum1.972,060.204,058.59
Rate as per item no 15.2.1 of SH : DismantlingRate as per item 15.2.1Sub-analysiscum0.352,434.25851.99
9999Removal of SFRC coverMaterialL.S.7.152.2716.23
9999Removal of M.S. foot restsMaterialL.S.8.092.2718.36
Rate as per Item No.19.24.4 of SH: DRAINAGERate as per item 19.24.4Sub-analysiseach-16,472.40-6,472.40
TOTAL
1,345.19
Add 1 % Water charges on “W-A”
0.35
TOTAL
1,345.54
Add GST on “X-A” (multiplying factor 0.2127)
7.43
TOTAL
1,352.97
Add 15% CPOH on “Y-A”
6.36
TOTAL
1,359.33
Add Cess @ 1% on “Z-A”
0.49
Cost of manhole 0.61m depth
1,359.82
Cost per metre depth
2,229.21
Say
2,229.20

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1760. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.