Extra for depth of manholes dismantled
- Item number
- 19.25.3
- Analysis basis
- 1.80 metre
- Priced inputs
- 2
- Derived rate
- ₹1,975.85/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.25.3 (Extra for depth of manholes dismantled : Rectangular arch type manhole 140x90 cm and beyond 2.45 m depth (up to 4.25 m depth)) is derived from 2 priced inputs for 1.80 metre and works out to ₹1,975.85 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- Dismantling IInd class brick work in
- cement mortar 1:4 (1 Cement : 4 Coarse
- sand) for 2.45 depth
- Qty for 2.45m depth
- 5.52mx0.23mx1.20m = 1.524 cum
- 3.92mx0.23mx1.15m = 1.037 cum
- Total = 2.561 cum
- 2x½x3.14x0.25mx0.23x0.1m = 0.018
- cum
- 2x3.14/4(0.15)²x0.23m = 0.008 cum
- Total deduction= = (-) 0.026 cum
- Net 2.561 - 0.026 = 2.535 cum Say 2.54
- cum
- Qty in arch
- ½x3.14x1.13x0.80x0.23m = 0.327 cum
- 2x½x3.14x0.25mx0.23x0.1m = 0.018
- cum
- Total = 0.345 cum Say 0.35 cum
- Totol for 4.45 m depth 2.54 + 0.35 = 2.89
- cum
- Qty for 4.25m depth
- 5.52mx0.23mx1.20m = 1.524 cum
- 3.92mx0.23mx2.95m = 2.660 cum
- Total = 4.184 cum
- 2x½x3.14x0.70mx0.23x0.1m = 0.051
- cum
- 2x3.14/4x(0.60)²x0.23 = 0.130 cum
- Total deduction== (-) 0.181 cum
- Net 4.184 - 0.181 = 4.003 cum Say 4.00
- cum
- Qty in arch
- ½x3.14x1.13x0.80x0.23m = 0.327 cum
- 2x½x3.14x0.70mx0.23x0.1m = 0.051
- cum
- Total = 0.378 cum Say 0.38 cum
- Total for 2.25 m depth = 4.0+ 0.38 =4.38
- cum
- Net difference = 4.38 - 2.89 = 1.49 cum
- Dismantling cement concrete 1:2:4 (1
- Cement : 2 coarse sand : 4 graded stone
- aggregate 40mm nominal size)
- Qty for 4.25m depth
- 2x1.4x(0.90/2)x(0.65+0.75)/2 = 0.882
- cum
- cum
- = 0.486 cum Say 0.49 cum
- Qty for 2.45m depth
- 2x1.4x(0.90/2)x(0.20+0.30)/2 = 0.315
- cum
- cum
- = 0.290 cum Say 0.29 cum
- Net difference = 0.49 - 0.29 = 0.20 cum
- Deduct arch ring and portion of pipe
- Deduct arch ring and portion of pipe
- Less pipe :1.4x3.14/4x(0.60)²(-) = 0.396
- Less pipe :1.4x3.14/4x(0.15)²(-) = 0.025
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per item no. 15.7.4 of SH :dismantling and dimolishingRate as per item 15.7.4 | cum | 1.49 | 2,060.20 | 3,069.70 | |
| SUB | Rate as per item no 15.2.1 of SH : Demolishing and dismantlingRate as per item 15.2.1 | cum | 0.2 | 2,434.25 | 486.85 |
- Cost for 1.8 metre depth
- 3,556.55
- Cost for 1 metre depth
- 1,975.86
- SAY
- ₹1,975.85
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1759
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1759. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.