Skip to main content
R/DAR 2023

Extra for depth of manholes dismantled

Rectangular manhole 120x90 cm and beyond 90 cm depth
Item number
19.25.2
Analysis basis
one metre
Priced inputs
2
Derived rate
₹2,436.90/ ONE METRE
D-01/RATE ANALYSISITEM 19.25.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.25.2 (Extra for depth of manholes dismantled : Rectangular manhole 120x90 cm and beyond 90 cm depth) is derived from 2 priced inputs for one metre and works out to ₹2,436.90 per one metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Dismantling of second class brick work
  • in cement mortar 1:5 (1 Cement : 5 fine
  • sand)
  • 5.12x0.23x1.0m = 1.178 cum Say 1.18
  • cum
ANALYSIS OF RATES · ITEM 19.25.2DETAILS OF COST FOR ONE METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per item no. 15.7.4 of SH :dismantling and dimolishingRate as per item 15.7.4cum1.182,060.202,431.04
9999MATRemoving of M.S. foot restsL.S.1.822.274.13
BUILD-UP TO RATE
TOTAL
2,435.17
Add 1 % Water charges on “W-A”
+0.04
TOTAL
2,435.21
Add GST on “X-A” (multiplying factor 0.2127)
+0.89
TOTAL
2,436.10
Add 15% CPOH on “Y-A”
+0.76
TOTAL
2,436.86
Add Cess @ 1% on “Z-A”
+0.06
Cost for one metre
2,436.92
SAY
₹2,436.90
D-02/SOURCEPRINTED PAGE 1759
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1759

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1759. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDRAINAGE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.