Providing and fixing in position pre-cast R.C.C. manhole cover and frame of required shape and approved quality M D - 10

Square shape 450 mm internal dimension
Item number
19.19.2.1
Analysis basis
one no
Priced inputs
4
Derived rate
₹1,386.55/ ONE NO
D-01/RATE ANALYSISITEM 19.19.2.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.19.2.1 (Providing and fixing in position pre-cast R.C.C. manhole cover and frame of required shape and approved quality M D - 10 Square shape 450 mm internal dimension) is derived from 4 priced inputs for one no and works out to ₹1,386.55 per one no after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement concrete 1:2:4 ( 1 cement : 2
  • coarse sand : 4 grade stone aggregate
  • 20 mm nominal size )
  • 0.95x0.95x0.15 = 0.1354 cum
  • 0.80x0.80x0.15 = (-) 0.096 cum
  • = 0.0394 cum Say 0.04 cum
  • Less cover with frame
ANALYSIS OF RATES · ITEM 19.19.2.1DETAILS OF COST FOR ONE NO
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7133MATRectangular shape 500x500 mm precast R.C.C. manhole cover with frame - M.D. - 10each1700.00700.00
9977MATCarriage of manhole coverL.S.6.762.2715.35
SUBRate as per item no. 4.1.3 of SH : Concrete WorkRate as per item 4.1.3cum0.047,878.50315.14
9999MATSundriesL.S.16.642.2737.77
BUILD-UP TO RATE
TOTAL
1,068.26
Add 1 % Water charges on “W-A”
+7.53
TOTAL
1,075.79
Add GST on “X-A” (multiplying factor 0.2127)
+161.79
TOTAL
1,237.58
Add 15% CPOH on “Y-A”
+138.37
TOTAL
1,375.95
Add Cess @ 1% on “Z-A”
+10.61
Cost for 1 no.
1,386.56
SAY
₹1,386.55
D-02/SOURCEPRINTED PAGE 1745
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1745

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1745. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDRAINAGE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.