Providing and fixing in position pre-cast R.C.C. manhole cover and frame of required shape and approved quality M D - 10
- Item number
- 19.19.2.2
- Analysis basis
- one no
- Priced inputs
- 4
- Derived rate
- ₹1,172.60/ ONE NO
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.19.2.2 (Providing and fixing in position pre-cast R.C.C. manhole cover and frame of required shape and approved quality M D - 10 Circular shape 500 mm internal diameter) is derived from 4 priced inputs for one no and works out to ₹1,172.60 per one no after water charges, GST, CPOH and cess. The full build-up is below.
- Cement concrete 1:2:4 ( 1 cement : 2
- coarse sand : 4 grade stone aggregate
- 20 mm nominal size )
- 3.14/4x(0.95)²x0.15 = 0.1064 cum
- 3.14/4x(0.8)²x0.15 = (-) 0.0754 cum
- = 0.031 cum Say 0.03 cum
- Less cover with frame
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7134 | MAT | Circular shape 500 mm dia precast R.C.C. manhole cover with frame - M.D. - 10Circular shape 500 mm dia precast R.C.C. manhole cover with frame- M.D.-10 | each | 1 | 605.00 | 605.00 |
| 9977 | MAT | Carriage of manhole cover | L.S. | 6.76 | 2.27 | 15.35 |
| SUB | Rate as per item no. 4.1.3 of SH : Concrete WorkRate as per item 4.1.3 | cum | 0.03 | 7,878.50 | 236.36 | |
| 9999 | MAT | Sundries | L.S. | 16.64 | 2.27 | 37.77 |
- TOTAL
- 894.48
- Add 1 % Water charges on “W-A”
- +6.58
- TOTAL
- 901.06
- Add GST on “X-A” (multiplying factor 0.2127)
- +141.38
- TOTAL
- 1,042.44
- Add 15% CPOH on “Y-A”
- +120.91
- TOTAL
- 1,163.35
- Add Cess @ 1% on “Z-A”
- +9.27
- Cost for 1 no.
- 1,172.62
- SAY
- ₹1,172.60
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1745
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1745. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.