Providing and fixing in position pre-cast R.C.C. manhole cover and frame of required shape and approved quality L D2.5

Circular shape 450 mm internal diameter

Item number
19.19.1.3
Analysis basis
Details of cost for one no.
Priced inputs
4
Derived rate
1,169.65 / one no

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.19.1.3 Providing and fixing in position pre-cast R.C.C. manhole cover and frame of required shape and approved quality L D2.5 Circular shape 450 mm internal diameter — is derived from 4 priced inputs for one no and works out to ₹1,169.65 per one no after water charges, GST, CPOH and cess. The full build-up is below.

  • Cement concrete 1:2:4 ( 1 cement : 2
  • coarse sand : 4 grade stone aggregate
  • 20 mm nominal size )
  • 3.14/4x(0.775)²x0.15 = 0.0708 cum
  • 3.14/4x(0.625)²x0.15 = (-) 0.0460 cum
  • = 0.0248 cum Say 0.03 cum
  • Less cover with frame
CodeInputUnitQuantityRate (INR)Amount (INR)
7132Circular shape 450 mm dia precast R.C.C. manhole cover with frame - L.D. - 2.5Materialeach1610.00610.00
9977Carriage of manhole coverMaterialL.S.6.762.2715.35
Rate as per item no. 4.1.3 of SH : Concrete WorkRate as per item 4.1.3Sub-analysiscum0.037,878.50236.36
9999SundriesMaterialL.S.13.522.2730.69
TOTAL
892.40
Add 1 % Water charges on “W-A”
6.56
TOTAL
898.96
Add GST on “X-A” (multiplying factor 0.2127)
140.94
TOTAL
1,039.90
Add 15% CPOH on “Y-A”
120.53
TOTAL
1,160.43
Add Cess @ 1% on “Z-A”
9.24
Cost for 1 no.
1,169.67
Say
1,169.65

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1744. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.