Supplying and fixing C.I. cover without frame for manholes

560 mm diameter C.I. cover (heavy duty) the weight of the cover to be not less than 108 kg
Item number
19.18.3
Analysis basis
one cover
Priced inputs
3
Derived rate
₹7,575.40/ ONE COVER
D-01/RATE ANALYSISITEM 19.18.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.18.3 (Supplying and fixing C.I. cover without frame for manholes : 560 mm diameter C.I. cover (heavy duty) the weight of the cover to be not less than 108 kg) is derived from 3 priced inputs for one cover and works out to ₹7,575.40 per one cover after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 19.18.3DETAILS OF COST FOR ONE COVER
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
3861MAT560 mm dia cover without frame (Heavy duty)each15,200.005,200.00
9977MATCarriage of C.I. coverL.S.16.122.2736.59
0114LABBeldarday0.12736.0088.32
BUILD-UP TO RATE
TOTAL
5,324.91
Add 1 % Water charges on “W”
+53.25
TOTAL
5,378.16
Add GST on “X-A” (multiplying factor 0.2127)
+1,143.93
TOTAL
6,522.09
Add 15% CPOH on “Y”
+978.31
TOTAL
7,500.40
Add Cess @ 1% on “Z”
+75.00
Cost for 1 no.
7,575.40
SAY
₹7,575.40
D-02/SOURCEPRINTED PAGE 1743
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1743

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1743. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.