R/DAR 2023

Providing and fixing in position pre-cast R.C.C. manhole cover and frame of required shape and approved quality L D2.5

Rectangular shape 600x450 mm internal dimensions
Item number
19.19.1.1
Analysis basis
one no
Priced inputs
4
Derived rate
₹1,437.65/ ONE NO
D-01/RATE ANALYSISITEM 19.19.1.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.19.1.1 (Providing and fixing in position pre-cast R.C.C. manhole cover and frame of required shape and approved quality L D2.5 Rectangular shape 600x450 mm internal dimensions) is derived from 4 priced inputs for one no and works out to ₹1,437.65 per one no after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement concrete 1:2:4 ( 1 cement : 2
  • coarse sand : 4 grade stone aggregate
  • 20 mm nominal size )
  • 1.00x0.85x0.15 = 0.1275 cum
  • (-) 0.0893 cum
  • = 0.0382 cum Say 0.04 cum
  • Less cover with frame 0.85x0.70x0.15 =
ANALYSIS OF RATES · ITEM 19.19.1.1DETAILS OF COST FOR ONE NO
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7130MATRectangular shape 600x450 mm precast R.C.C. manhole cover with frame - L.D. - 2.5each1743.00743.00
SUBRate as per item no. 4.1.3 of SH : Concrete WorkRate as per item 4.1.3cum0.047,878.50315.14
9977MATCarriage of R.C.C cover with frameL.S.6.762.2715.35
9999MATSundriesL.S.13.522.2730.69
BUILD-UP TO RATE
TOTAL
1,104.18
Add 1 % Water charges on “W-A”
+7.89
TOTAL
1,112.07
Add GST on “X-A” (multiplying factor 0.2127)
+169.51
TOTAL
1,281.58
Add 15% CPOH on “Y-A”
+144.97
TOTAL
1,426.55
Add Cess @ 1% on “Z-A”
+11.11
Cost for 1 no.
1,437.66
SAY
₹1,437.65
D-02/SOURCEPRINTED PAGE 1743
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1743

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1743. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.