CPWD Analysis of Rates · Drainage
Providing and fixing in position pre-cast R.C.C. manhole cover and frame of required shape and approved quality L D2.5
Rectangular shape 600x450 mm internal dimensions
- Item number
- 19.19.1.1
- Analysis basis
- Details of cost for one no.
- Priced inputs
- 4
- Derived rate
- ₹1,437.65 / one no
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.19.1.1 — Providing and fixing in position pre-cast R.C.C. manhole cover and frame of required shape and approved quality L D2.5 Rectangular shape 600x450 mm internal dimensions — is derived from 4 priced inputs for one no and works out to ₹1,437.65 per one no after water charges, GST, CPOH and cess. The full build-up is below.
- Cement concrete 1:2:4 ( 1 cement : 2
- coarse sand : 4 grade stone aggregate
- 20 mm nominal size )
- 1.00x0.85x0.15 = 0.1275 cum
- (-) 0.0893 cum
- = 0.0382 cum Say 0.04 cum
- Less cover with frame 0.85x0.70x0.15 =
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7130 | Rectangular shape 600x450 mm precast R.C.C. manhole cover with frame - L.D. - 2.5Material | each | 1 | 743.00 | 743.00 |
| Rate as per item no. 4.1.3 of SH : Concrete WorkRate as per item 4.1.3Sub-analysis | cum | 0.04 | 7,878.50 | 315.14 | |
| 9977 | Carriage of R.C.C cover with frameMaterial | L.S. | 6.76 | 2.27 | 15.35 |
| 9999 | SundriesMaterial | L.S. | 13.52 | 2.27 | 30.69 |
- TOTAL
- 1,104.18
- Add 1 % Water charges on “W-A”
- 7.89
- TOTAL
- 1,112.07
- Add GST on “X-A” (multiplying factor 0.2127)
- 169.51
- TOTAL
- 1,281.58
- Add 15% CPOH on “Y-A”
- 144.97
- TOTAL
- 1,426.55
- Add Cess @ 1% on “Z-A”
- 11.11
- Cost for 1 no.
- 1,437.66
- Say
- 1,437.65
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1743. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works