CPWD Analysis of Rates · Drainage

Providing and fixing in position pre-cast R.C.C. manhole cover and frame of required shape and approved quality L D2.5

Rectangular shape 600x450 mm internal dimensions

Item number
19.19.1.1
Analysis basis
Details of cost for one no.
Priced inputs
4
Derived rate
1,437.65 / one no

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.19.1.1 Providing and fixing in position pre-cast R.C.C. manhole cover and frame of required shape and approved quality L D2.5 Rectangular shape 600x450 mm internal dimensions — is derived from 4 priced inputs for one no and works out to ₹1,437.65 per one no after water charges, GST, CPOH and cess. The full build-up is below.

  • Cement concrete 1:2:4 ( 1 cement : 2
  • coarse sand : 4 grade stone aggregate
  • 20 mm nominal size )
  • 1.00x0.85x0.15 = 0.1275 cum
  • (-) 0.0893 cum
  • = 0.0382 cum Say 0.04 cum
  • Less cover with frame 0.85x0.70x0.15 =
CodeInputUnitQuantityRate (INR)Amount (INR)
7130Rectangular shape 600x450 mm precast R.C.C. manhole cover with frame - L.D. - 2.5Materialeach1743.00743.00
Rate as per item no. 4.1.3 of SH : Concrete WorkRate as per item 4.1.3Sub-analysiscum0.047,878.50315.14
9977Carriage of R.C.C cover with frameMaterialL.S.6.762.2715.35
9999SundriesMaterialL.S.13.522.2730.69
TOTAL
1,104.18
Add 1 % Water charges on “W-A”
7.89
TOTAL
1,112.07
Add GST on “X-A” (multiplying factor 0.2127)
169.51
TOTAL
1,281.58
Add 15% CPOH on “Y-A”
144.97
TOTAL
1,426.55
Add Cess @ 1% on “Z-A”
11.11
Cost for 1 no.
1,437.66
Say
1,437.65

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1743. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.