Skip to main content
R/DAR 2023

Supplying and fixing C.I. cover without frame for manholes

455x610 mm rectangular C.I. cover (light duty) the weight of the cover to be not less than 23 kg
Item number
19.18.1
Analysis basis
one cover
Priced inputs
3
Derived rate
₹1,358.00/ ONE COVER
D-01/RATE ANALYSISITEM 19.18.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.18.1 (Supplying and fixing C.I. cover without frame for manholes : 455x610 mm rectangular C.I. cover (light duty) the weight of the cover to be not less than 23 kg) is derived from 3 priced inputs for one cover and works out to ₹1,358.00 per one cover after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 19.18.1DETAILS OF COST FOR ONE COVER
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1355MATRectangular cover 455x610mm without frame (low duty)C.I. Rectangular cover 455x610 mm without frame (low duty)each1850.00850.00
9977MATCarriage of C.I. Manhole coverL.S.7.152.2716.23
0114LABBeldarday0.12736.0088.32
BUILD-UP TO RATE
TOTAL
954.55
Add 1 % Water charges on “W”
+9.55
TOTAL
964.10
Add GST on “X-A” (multiplying factor 0.2127)
+205.06
TOTAL
1,169.16
Add 15% CPOH on “Y”
+175.37
TOTAL
1,344.53
Add Cess @ 1% on “Z”
+13.45
Cost for 1 cover
1,357.98
SAY
₹1,358.00
D-02/SOURCEPRINTED PAGE 1742
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1742

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1742. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDRAINAGE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.