Providing, laying and jointing glazed stoneware pipes class SP-1 with stiff mixture of cement mortar in the proportion of 1:1 (1 cement : 1 fine sand) including testing of joints etc. complete

300 mm diameter
Item number
19.1.5
Analysis basis
30 metre
Priced inputs
9
Derived rate
₹2,064.15/ METRE
D-01/RATE ANALYSISITEM 19.1.5

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.1.5 (Providing, laying and jointing glazed stoneware pipes class SP-1 with stiff mixture of cement mortar in the proportion of 1:1 (1 cement : 1 fine sand) including testing of joints etc. complete : 300 mm diameter) is derived from 9 priced inputs for 30 metre and works out to ₹2,064.15 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Added 10% allowance for breakage
  • Cement of 50 joints = 0.125 tonne
  • or plain gaskin @ 0.36 kg / joint
  • = 0.36x50 =18.00 kg
ANALYSIS OF RATES · ITEM 19.1.5DETAILS OF COST FOR 30 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1859MATStoneware pipes grade A (60 cm long) 300 mm diaeach55578.0031,790.00
0367MATPortland Cement (OPC-43 grade)tonne0.1255,156.00644.50
0983MATFine sand (zone IV)cum0.075980.0073.50
2261MATCarriage of Fine sand (1 part badarpur———
1881MATSpun yarnkilogram1861.001,098.00
0123LABMason 1st classMason 1st classday2.5897.002,242.50
0124LABMason 2nd classMason 2nd classday2.5816.002,040.00
0114LABBeldarday6736.004,416.00
0101LABBhistiday1.5816.001,224.00
BUILD-UP TO RATE
TOTAL
43,528.50
Add 1 % Water charges on “W”
+435.29
TOTAL
43,963.79
Add GST on “X” (multiplying factor 0.2127)
+9,351.10
TOTAL
53,314.89
Add 15% CPOH on “Y”
+7,997.23
TOTAL
61,312.12
Add Cess @ 1% on “Z”
+613.12
Cost of 30 metre
61,925.24
Cost of 1 metre
2,064.17
SAY
₹2,064.15
D-02/SOURCEPRINTED PAGE 1693
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1693

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1693. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDRAINAGE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.