CPWD Analysis of Rates · Drainage
Providing, laying and jointing glazed stoneware pipes class SP-1 with stiff mixture of cement mortar in the proportion of 1:1 (1 cement : 1 fine sand) including testing of joints etc. complete
300 mm diameter
- Item number
- 19.1.5
- Analysis basis
- Details of cost for 30 metre
- Priced inputs
- 9
- Derived rate
- ₹2,064.15 / metre
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.1.5 — Providing, laying and jointing glazed stoneware pipes class SP-1 with stiff mixture of cement mortar in the proportion of 1:1 (1 cement : 1 fine sand) including testing of joints etc. complete : 300 mm diameter — is derived from 9 priced inputs for 30 metre and works out to ₹2,064.15 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- Added 10% allowance for breakage
- Cement of 50 joints = 0.125 tonne
- or plain gaskin @ 0.36 kg / joint
- = 0.36x50 =18.00 kg
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1859 | Stoneware pipes grade A (60 cm long) 300 mm diaMaterial | each | 55 | 578.00 | 31,790.00 |
| 0367 | Portland Cement (OPC-43 grade)Material | tonne | 0.125 | 5,156.00 | 644.50 |
| 0983 | Fine sand (zone IV)Material | cum | 0.075 | 980.00 | 73.50 |
| 2261 | Carriage of Fine sand (1 part badarpurMaterial | NaN | NaN | NaN | |
| 1881 | Spun yarnMaterial | kilogram | 18 | 61.00 | 1,098.00 |
| 0123 | Mason 1st classMason 1st classLabour | day | 2.5 | 897.00 | 2,242.50 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 2.5 | 816.00 | 2,040.00 |
| 0114 | BeldarLabour | day | 6 | 736.00 | 4,416.00 |
| 0101 | BhistiLabour | day | 1.5 | 816.00 | 1,224.00 |
- TOTAL
- 43,528.50
- Add 1 % Water charges on “W”
- 435.29
- TOTAL
- 43,963.79
- Add GST on “X” (multiplying factor 0.2127)
- 9,351.10
- TOTAL
- 53,314.89
- Add 15% CPOH on “Y”
- 7,997.23
- TOTAL
- 61,312.12
- Add Cess @ 1% on “Z”
- 613.12
- Cost of 30 metre
- 61,925.24
- Cost of 1 metre
- 2,064.17
- Say
- 2,064.15
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1693. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works