Providing, laying and jointing glazed stoneware pipes class SP-1 with stiff mixture of cement mortar in the proportion of 1:1 (1 cement : 1 fine sand) including testing of joints etc. complete

250 mm diameter
Item number
19.1.4
Analysis basis
30 metre
Priced inputs
8
Derived rate
₹1,505.60/ METRE
D-01/RATE ANALYSISITEM 19.1.4

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.1.4 (Providing, laying and jointing glazed stoneware pipes class SP-1 with stiff mixture of cement mortar in the proportion of 1:1 (1 cement : 1 fine sand) including testing of joints etc. complete : 250 mm diameter) is derived from 8 priced inputs for 30 metre and works out to ₹1,505.60 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Added 10% allowance for breakage
  • Cement of 50 joints = 0.094 tonne
  • or plain gaskin @ 0.30 kg per joint =
  • 0.30x50= 15.00 kg
ANALYSIS OF RATES · ITEM 19.1.4DETAILS OF COST FOR 30 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1858MATStoneware pipes grade A (60 cm long) 250 mm diaeach55385.0021,175.00
0367MATPortland Cement (OPC-43 grade)tonne0.0945,156.00484.66
0983MATFine sand (zone IV)cum0.05980.0049.00
1881MATSpun yarnkilogram1561.00915.00
0123LABMason 1st classMason 1st classday2.25897.002,018.25
0124LABMason 2nd classMason 2nd classday2.25816.001,836.00
0114LABBeldarday5.5736.004,048.00
0101LABBhistiday1.5816.001,224.00
BUILD-UP TO RATE
TOTAL
31,749.91
Add 1 % Water charges on “W”
+317.50
TOTAL
32,067.41
Add GST on “X” (multiplying factor 0.2127)
+6,820.74
TOTAL
38,888.15
Add 15% CPOH on “Y”
+5,833.22
TOTAL
44,721.37
Add Cess @ 1% on “Z”
+447.21
Cost of 30 metre
45,168.58
Cost of 1 metre
1,505.62
SAY
₹1,505.60
D-02/SOURCEPRINTED PAGE 1692
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1692

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1692. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.