Providing, laying and jointing glazed stoneware pipes class SP-1 with stiff mixture of cement mortar in the proportion of 1:1 (1 cement : 1 fine sand) including testing of joints etc. complete
- Item number
- 19.1.4
- Analysis basis
- 30 metre
- Priced inputs
- 8
- Derived rate
- ₹1,505.60/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.1.4 (Providing, laying and jointing glazed stoneware pipes class SP-1 with stiff mixture of cement mortar in the proportion of 1:1 (1 cement : 1 fine sand) including testing of joints etc. complete : 250 mm diameter) is derived from 8 priced inputs for 30 metre and works out to ₹1,505.60 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- Added 10% allowance for breakage
- Cement of 50 joints = 0.094 tonne
- or plain gaskin @ 0.30 kg per joint =
- 0.30x50= 15.00 kg
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1858 | MAT | Stoneware pipes grade A (60 cm long) 250 mm dia | each | 55 | 385.00 | 21,175.00 |
| 0367 | MAT | Portland Cement (OPC-43 grade) | tonne | 0.094 | 5,156.00 | 484.66 |
| 0983 | MAT | Fine sand (zone IV) | cum | 0.05 | 980.00 | 49.00 |
| 1881 | MAT | Spun yarn | kilogram | 15 | 61.00 | 915.00 |
| 0123 | LAB | Mason 1st classMason 1st class | day | 2.25 | 897.00 | 2,018.25 |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 2.25 | 816.00 | 1,836.00 |
| 0114 | LAB | Beldar | day | 5.5 | 736.00 | 4,048.00 |
| 0101 | LAB | Bhisti | day | 1.5 | 816.00 | 1,224.00 |
- TOTAL
- 31,749.91
- Add 1 % Water charges on “W”
- +317.50
- TOTAL
- 32,067.41
- Add GST on “X” (multiplying factor 0.2127)
- +6,820.74
- TOTAL
- 38,888.15
- Add 15% CPOH on “Y”
- +5,833.22
- TOTAL
- 44,721.37
- Add Cess @ 1% on “Z”
- +447.21
- Cost of 30 metre
- 45,168.58
- Cost of 1 metre
- 1,505.62
- SAY
- ₹1,505.60
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1692
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1692. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.