Providing, laying and jointing glazed stoneware pipes class SP-1 with stiff mixture of cement mortar in the proportion of 1:1 (1 cement : 1 fine sand) including testing of joints etc. complete

250 mm diameter

Item number
19.1.4
Analysis basis
Details of cost for 30 metre
Priced inputs
8
Derived rate
1,505.60 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.1.4 Providing, laying and jointing glazed stoneware pipes class SP-1 with stiff mixture of cement mortar in the proportion of 1:1 (1 cement : 1 fine sand) including testing of joints etc. complete : 250 mm diameter — is derived from 8 priced inputs for 30 metre and works out to ₹1,505.60 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • Added 10% allowance for breakage
  • Cement of 50 joints = 0.094 tonne
  • or plain gaskin @ 0.30 kg per joint =
  • 0.30x50= 15.00 kg
CodeInputUnitQuantityRate (INR)Amount (INR)
1858Stoneware pipes grade A (60 cm long) 250 mm diaMaterialeach55385.0021,175.00
0367Portland Cement (OPC-43 grade)Materialtonne0.0945,156.00484.66
0983Fine sand (zone IV)Materialcum0.05980.0049.00
1881Spun yarnMaterialkilogram1561.00915.00
0123Mason 1st classMason 1st classLabourday2.25897.002,018.25
0124Mason 2nd classMason 2nd classLabourday2.25816.001,836.00
0114BeldarLabourday5.5736.004,048.00
0101BhistiLabourday1.5816.001,224.00
TOTAL
31,749.91
Add 1 % Water charges on “W”
317.50
TOTAL
32,067.41
Add GST on “X” (multiplying factor 0.2127)
6,820.74
TOTAL
38,888.15
Add 15% CPOH on “Y”
5,833.22
TOTAL
44,721.37
Add Cess @ 1% on “Z”
447.21
Cost of 30 metre
45,168.58
Cost of 1 metre
1,505.62
Say
1,505.60

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1692. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.