Providing, laying and jointing glazed stoneware pipes class SP-1 with stiff mixture of cement mortar in the proportion of 1:1 (1 cement : 1 fine sand) including testing of joints etc. complete

200 mm diameter
Item number
19.1.3
Analysis basis
30 metre
Priced inputs
8
Derived rate
₹970.35/ METRE
D-01/RATE ANALYSISITEM 19.1.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.1.3 (Providing, laying and jointing glazed stoneware pipes class SP-1 with stiff mixture of cement mortar in the proportion of 1:1 (1 cement : 1 fine sand) including testing of joints etc. complete : 200 mm diameter) is derived from 8 priced inputs for 30 metre and works out to ₹970.35 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Added 10% allowance for breakage
  • Cement of 50 joints = 0.053 tonne
  • or plain gaskin @ 0.24 kg per joint =
  • 0.24x50 =12.00 kg
ANALYSIS OF RATES · ITEM 19.1.3DETAILS OF COST FOR 30 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1856MATStoneware pipes grade A (60 cm long) 200 mm diaeach55220.0012,100.00
0367MATPortland Cement (OPC-43 grade)tonne0.0535,156.00273.27
0983MATFine sand (zone IV)cum0.028980.0027.44
1881MATSpun yarnkilogram1261.00732.00
0123LABMason 1st classMason 1st classday1.75897.001,569.75
0124LABMason 2nd classMason 2nd classday1.75816.001,428.00
0114LABBeldarday4.5736.003,312.00
0101LABBhistiday1.25816.001,020.00
BUILD-UP TO RATE
TOTAL
20,462.46
Add 1 % Water charges on “W”
+204.62
TOTAL
20,667.08
Add GST on “X” (multiplying factor 0.2127)
+4,395.89
TOTAL
25,062.97
Add 15% CPOH on “Y”
+3,759.45
TOTAL
28,822.42
Add Cess @ 1% on “Z”
+288.22
Cost of 30 metre
29,110.64
Cost of 1 metre
970.35
SAY
₹970.35
D-02/SOURCEPRINTED PAGE 1692
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1692

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1692. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.