Providing, laying and jointing glazed stoneware pipes class SP-1 with stiff mixture of cement mortar in the proportion of 1:1 (1 cement : 1 fine sand) including testing of joints etc. complete

200 mm diameter

Item number
19.1.3
Analysis basis
Details of cost for 30 metre
Priced inputs
8
Derived rate
970.35 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.1.3 Providing, laying and jointing glazed stoneware pipes class SP-1 with stiff mixture of cement mortar in the proportion of 1:1 (1 cement : 1 fine sand) including testing of joints etc. complete : 200 mm diameter — is derived from 8 priced inputs for 30 metre and works out to ₹970.35 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • Added 10% allowance for breakage
  • Cement of 50 joints = 0.053 tonne
  • or plain gaskin @ 0.24 kg per joint =
  • 0.24x50 =12.00 kg
CodeInputUnitQuantityRate (INR)Amount (INR)
1856Stoneware pipes grade A (60 cm long) 200 mm diaMaterialeach55220.0012,100.00
0367Portland Cement (OPC-43 grade)Materialtonne0.0535,156.00273.27
0983Fine sand (zone IV)Materialcum0.028980.0027.44
1881Spun yarnMaterialkilogram1261.00732.00
0123Mason 1st classMason 1st classLabourday1.75897.001,569.75
0124Mason 2nd classMason 2nd classLabourday1.75816.001,428.00
0114BeldarLabourday4.5736.003,312.00
0101BhistiLabourday1.25816.001,020.00
TOTAL
20,462.46
Add 1 % Water charges on “W”
204.62
TOTAL
20,667.08
Add GST on “X” (multiplying factor 0.2127)
4,395.89
TOTAL
25,062.97
Add 15% CPOH on “Y”
3,759.45
TOTAL
28,822.42
Add Cess @ 1% on “Z”
288.22
Cost of 30 metre
29,110.64
Cost of 1 metre
970.35
Say
970.35

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1692. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.