Providing, laying and jointing glazed stoneware pipes class SP-1 with stiff mixture of cement mortar in the proportion of 1:1 (1 cement : 1 fine sand) including testing of joints etc. complete

150 mm diameter
Item number
19.1.2
Analysis basis
30 metre
Priced inputs
8
Derived rate
₹695.80/ METRE
D-01/RATE ANALYSISITEM 19.1.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.1.2 (Providing, laying and jointing glazed stoneware pipes class SP-1 with stiff mixture of cement mortar in the proportion of 1:1 (1 cement : 1 fine sand) including testing of joints etc. complete : 150 mm diameter) is derived from 8 priced inputs for 30 metre and works out to ₹695.80 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Added 10% allowance for breakage
  • Cement of 50 joints = 0.036 tonne
  • or plain gaskin @ 0.18 kg per joint =
  • 0.18x50 = 9 kg
ANALYSIS OF RATES · ITEM 19.1.2DETAILS OF COST FOR 30 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1855MATStoneware pipes grade A (60 cm long) 150 mm diaeach55138.007,590.00
0367MATPortland Cement (OPC-43 grade)tonne0.0365,156.00185.62
0983MATFine sand (zone IV)cum0.019980.0018.62
1881MATSpun yarnkilogram961.00549.00
0123LABMason 1st classMason 1st classday1.5897.001,345.50
0124LABMason 2nd classMason 2nd classday1.5816.001,224.00
0114LABBeldarday4736.002,944.00
0101LABBhistiday1816.00816.00
BUILD-UP TO RATE
TOTAL
14,672.74
Add 1 % Water charges on “W”
+146.73
TOTAL
14,819.47
Add GST on “X” (multiplying factor 0.2127)
+3,152.10
TOTAL
17,971.57
Add 15% CPOH on “Y”
+2,695.74
TOTAL
20,667.31
Add Cess @ 1% on “Z”
+206.67
Cost of 30 metre
20,873.98
Cost of 1 metre
695.80
SAY
₹695.80
D-02/SOURCEPRINTED PAGE 1691
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1691

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1691. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDRAINAGE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.