Providing, laying and jointing glazed stoneware pipes class SP-1 with stiff mixture of cement mortar in the proportion of 1:1 (1 cement : 1 fine sand) including testing of joints etc. complete
- Item number
- 19.1.2
- Analysis basis
- 30 metre
- Priced inputs
- 8
- Derived rate
- ₹695.80/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.1.2 (Providing, laying and jointing glazed stoneware pipes class SP-1 with stiff mixture of cement mortar in the proportion of 1:1 (1 cement : 1 fine sand) including testing of joints etc. complete : 150 mm diameter) is derived from 8 priced inputs for 30 metre and works out to ₹695.80 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- Added 10% allowance for breakage
- Cement of 50 joints = 0.036 tonne
- or plain gaskin @ 0.18 kg per joint =
- 0.18x50 = 9 kg
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1855 | MAT | Stoneware pipes grade A (60 cm long) 150 mm dia | each | 55 | 138.00 | 7,590.00 |
| 0367 | MAT | Portland Cement (OPC-43 grade) | tonne | 0.036 | 5,156.00 | 185.62 |
| 0983 | MAT | Fine sand (zone IV) | cum | 0.019 | 980.00 | 18.62 |
| 1881 | MAT | Spun yarn | kilogram | 9 | 61.00 | 549.00 |
| 0123 | LAB | Mason 1st classMason 1st class | day | 1.5 | 897.00 | 1,345.50 |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 1.5 | 816.00 | 1,224.00 |
| 0114 | LAB | Beldar | day | 4 | 736.00 | 2,944.00 |
| 0101 | LAB | Bhisti | day | 1 | 816.00 | 816.00 |
- TOTAL
- 14,672.74
- Add 1 % Water charges on “W”
- +146.73
- TOTAL
- 14,819.47
- Add GST on “X” (multiplying factor 0.2127)
- +3,152.10
- TOTAL
- 17,971.57
- Add 15% CPOH on “Y”
- +2,695.74
- TOTAL
- 20,667.31
- Add Cess @ 1% on “Z”
- +206.67
- Cost of 30 metre
- 20,873.98
- Cost of 1 metre
- 695.80
- SAY
- ₹695.80
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1691
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1691. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.