CPWD Analysis of Rates · Drainage

Providing, laying and jointing glazed stoneware pipes class SP-1 with stiff mixture of cement mortar in the proportion of 1:1 (1 cement : 1 fine sand) including testing of joints etc. complete

150 mm diameter

Item number
19.1.2
Analysis basis
Details of cost for 30 metre
Priced inputs
8
Derived rate
695.80 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.1.2 Providing, laying and jointing glazed stoneware pipes class SP-1 with stiff mixture of cement mortar in the proportion of 1:1 (1 cement : 1 fine sand) including testing of joints etc. complete : 150 mm diameter — is derived from 8 priced inputs for 30 metre and works out to ₹695.80 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • Added 10% allowance for breakage
  • Cement of 50 joints = 0.036 tonne
  • or plain gaskin @ 0.18 kg per joint =
  • 0.18x50 = 9 kg
CodeInputUnitQuantityRate (INR)Amount (INR)
1855Stoneware pipes grade A (60 cm long) 150 mm diaMaterialeach55138.007,590.00
0367Portland Cement (OPC-43 grade)Materialtonne0.0365,156.00185.62
0983Fine sand (zone IV)Materialcum0.019980.0018.62
1881Spun yarnMaterialkilogram961.00549.00
0123Mason 1st classMason 1st classLabourday1.5897.001,345.50
0124Mason 2nd classMason 2nd classLabourday1.5816.001,224.00
0114BeldarLabourday4736.002,944.00
0101BhistiLabourday1816.00816.00
TOTAL
14,672.74
Add 1 % Water charges on “W”
146.73
TOTAL
14,819.47
Add GST on “X” (multiplying factor 0.2127)
3,152.10
TOTAL
17,971.57
Add 15% CPOH on “Y”
2,695.74
TOTAL
20,667.31
Add Cess @ 1% on “Z”
206.67
Cost of 30 metre
20,873.98
Cost of 1 metre
695.80
Say
695.80

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1691. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.