CPWD Analysis of Rates · Drainage

Providing, laying and jointing glazed stoneware pipes class SP-1 with stiff mixture of cement mortar in the proportion of 1:1 (1 cement : 1 fine sand) including testing of joints etc. complete

100 mm diameter

Item number
19.1.1
Analysis basis
Details of cost for 30 metre
Priced inputs
8
Derived rate
443.60 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.1.1 Providing, laying and jointing glazed stoneware pipes class SP-1 with stiff mixture of cement mortar in the proportion of 1:1 (1 cement : 1 fine sand) including testing of joints etc. complete : 100 mm diameter — is derived from 8 priced inputs for 30 metre and works out to ₹443.60 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • Added 10% allowance for breakage
  • Cement for 50 joints = 0.019 tonne
  • or plain gaskin @ 0.09 kg per joint =
  • 0.09x50 = 4.50 kg
CodeInputUnitQuantityRate (INR)Amount (INR)
1854Stoneware pipes grade A (60 cm long) 100 mm diaMaterialeach5577.004,235.00
0367Portland Cement (OPC-43 grade)Materialtonne0.0195,156.0097.96
0983Fine sand (zone IV)Materialcum0.01980.009.80
1881Spun yarnMaterialkilogram4.561.00274.50
0123Mason 1st classMason 1st classLabourday1897.00897.00
0124Mason 2nd classMason 2nd classLabourday1816.00816.00
0114BeldarLabourday3736.002,208.00
0101BhistiLabourday1816.00816.00
TOTAL
9,354.26
Add 1 % Water charges on “W”
93.54
TOTAL
9,447.80
Add GST on “X” (multiplying factor 0.2127)
2,009.55
TOTAL
11,457.35
Add 15% CPOH on “Y”
1,718.60
TOTAL
13,175.95
Add Cess @ 1% on “Z”
131.76
Cost of 30 metre
13,307.71
Cost of 1 metre
443.59
Say
443.60

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1691. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.