Skip to main content
R/DAR 2023

Providing, laying and jointing glazed stoneware pipes class SP-1 with stiff mixture of cement mortar in the proportion of 1:1 (1 cement : 1 fine sand) including testing of joints etc. complete

100 mm diameter
Item number
19.1.1
Analysis basis
30 metre
Priced inputs
8
Derived rate
₹443.60/ METRE
D-01/RATE ANALYSISITEM 19.1.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.1.1 (Providing, laying and jointing glazed stoneware pipes class SP-1 with stiff mixture of cement mortar in the proportion of 1:1 (1 cement : 1 fine sand) including testing of joints etc. complete : 100 mm diameter) is derived from 8 priced inputs for 30 metre and works out to ₹443.60 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Added 10% allowance for breakage
  • Cement for 50 joints = 0.019 tonne
  • or plain gaskin @ 0.09 kg per joint =
  • 0.09x50 = 4.50 kg
ANALYSIS OF RATES · ITEM 19.1.1DETAILS OF COST FOR 30 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1854MATStoneware pipes grade A (60 cm long) 100 mm diaeach5577.004,235.00
0367MATPortland Cement (OPC-43 grade)tonne0.0195,156.0097.96
0983MATFine sand (zone IV)cum0.01980.009.80
1881MATSpun yarnkilogram4.561.00274.50
0123LABMason 1st classMason 1st classday1897.00897.00
0124LABMason 2nd classMason 2nd classday1816.00816.00
0114LABBeldarday3736.002,208.00
0101LABBhistiday1816.00816.00
BUILD-UP TO RATE
TOTAL
9,354.26
Add 1 % Water charges on “W”
+93.54
TOTAL
9,447.80
Add GST on “X” (multiplying factor 0.2127)
+2,009.55
TOTAL
11,457.35
Add 15% CPOH on “Y”
+1,718.60
TOTAL
13,175.95
Add Cess @ 1% on “Z”
+131.76
Cost of 30 metre
13,307.71
Cost of 1 metre
443.59
SAY
₹443.60
D-02/SOURCEPRINTED PAGE 1691
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1691

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1691. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDRAINAGE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.