Skip to main content
R/DAR 2023

Providing and laying cement concrete 1:5:10 (1 cement : 5 coarse sand : 10 graded stone aggregate 40 mm nominal size) all-round S.W. pipes including bed concrete as per standard design

100 mm diameter S.W. pipe
Item number
19.2.1
Analysis basis
10 metre
Priced inputs
1
Derived rate
₹964.75/ METRE
D-01/RATE ANALYSISITEM 19.2.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.2.1 (Providing and laying cement concrete 1:5:10 (1 cement : 5 coarse sand : 10 graded stone aggregate 40 mm nominal size) all-round S.W. pipes including bed concrete as per standard design : 100 mm diameter S.W. pipe) is derived from 1 priced inputs for 10 metre and works out to ₹964.75 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Area = W x W/2 + ½ x (3.14 x W² / 4) (3.14 x D² / 4)
  • = W² x (0.5 + 3.14 / 8) - (3.14 x D² / 4)
  • Where W = D + X
  • D = 100 + 12 + 12 = 124 mm or 12.4 cm
  • X = 300 mm as trench depth is less than
  • 1200 mm
  • W = 12.4 + 30 = 42.4
  • Area= 42.4² x ( 0.5 + 3.14/ 8) - (3.14 x
  • 12.4²/4)
  • = 1484 sqcm = 0.1484 sqm Say 0.148 sqm
  • For 10 m length qty. of concrete reqd. =
  • 1.48 cum
ANALYSIS OF RATES · ITEM 19.2.1DETAILS OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per item no 4.1.10 of SH : Concrete WorkRate as per item 4.1.10cum1.486,518.609,647.53
BUILD-UP TO RATE
Cost of 10 metre
9,647.53
Cost of metre
964.75
SAY
₹964.75
D-02/SOURCEPRINTED PAGE 1693
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1693

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1693. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDRAINAGE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.