Skip to main content

CPWD Analysis of Rates · Concrete Work

Providing and fixing up to floor five level precast cement concrete hollow block, including hoisting and setting in position with cement mortar 1:3 (1 cement : 3 coarse sand), cost of required centering, shuttering complete

1:1½:3 (1 Cement: 1½ coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)

Item number
4.8.1
Analysis basis
Details of cost for one block of overall size
Priced inputs
6
Derived rate
14,624.20 / one block

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.8.1 Providing and fixing up to floor five level precast cement concrete hollow block, including hoisting and setting in position with cement mortar 1:3 (1 cement : 3 coarse sand), cost of required centering, shuttering complete 1:1½:3 (1 Cement: 1½ coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) — is derived from 6 priced inputs for one block and works out to ₹14,624.20 per one block after water charges, GST, CPOH and cess. The full build-up is below.

  • 1m x 0.50m and 0.10m thick having 6 vertical
  • hollows, 40x20x30cm finished contents = 1mx0.5mx0.1m = 0.05cum
  • Cement concrete 1:1.5:3
  • Net qty = 0.05[6x0.5x{2x1/2(0.05+7)}x0.074] =
  • 0.023cum
  • Cement mortar 1:2 for fixing
  • Extra Labour for lifting material upto floor V
  • level
  • Labour for hoisting and setting in position
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per Item No.4.1.2 of SH:Concrete WorkRate as per item 4.1.2Sub-analysiscum0.0238,340.85191.84
9999Centering and shuttering including T&P charges, hire charges of steel mould, table vibrator, rammer, bolts nuts & washers etcMaterialL.S.26.912.2761.09
Rate as per Item No.3.7 of SH:MortarsRate as per item 3.7Sub-analysiscum0.0025,584.5011.17
0115CoolieLabourday0.056736.0041.22
0123Mason (brick layer) 1st classMason 1st classLabourday0.05897.0044.85
0114BeldarLabourday0.3736.00220.80
TOTAL
570.97
Add 1 % Water charges on “W-A”
3.79
TOTAL
574.76
Add GST on “X-A” (multiplying factor 0.2127)
81.45
TOTAL
656.21
Add 15% CPOH on “Y-A”
69.66
TOTAL
725.87
Add Cess @ 1% on “Z-A”
5.34
Cost for 0.05 cum.
731.21
Cost per cum.
14,624.20
Say
14,624.20

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 179. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works