Providing and fixing up to floor five level precast cement concrete hollow block, including hoisting and setting in position with cement mortar 1:3 (1 cement : 3 coarse sand), cost of required centering, shuttering complete
- Item number
- 4.8.1
- Analysis basis
- one block
- Priced inputs
- 6
- Derived rate
- ₹14,624.20/ ONE BLOCK
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.8.1 (Providing and fixing up to floor five level precast cement concrete hollow block, including hoisting and setting in position with cement mortar 1:3 (1 cement : 3 coarse sand), cost of required centering, shuttering complete 1:1½:3 (1 Cement: 1½ coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)) is derived from 6 priced inputs for one block and works out to ₹14,624.20 per one block after water charges, GST, CPOH and cess. The full build-up is below.
- 1m x 0.50m and 0.10m thick having 6 vertical
- hollows, 40x20x30cm finished contents = 1mx0.5mx0.1m = 0.05cum
- Cement concrete 1:1.5:3
- Net qty = 0.05[6x0.5x{2x1/2(0.05+7)}x0.074] =
- 0.023cum
- Cement mortar 1:2 for fixing
- Extra Labour for lifting material upto floor V
- level
- Labour for hoisting and setting in position
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per Item No.4.1.2 of SH:Concrete WorkRate as per item 4.1.2 | cum | 0.023 | 8,340.85 | 191.84 | |
| 9999 | MAT | Centering and shuttering including T&P charges, hire charges of steel mould, table vibrator, rammer, bolts nuts & washers etc | L.S. | 26.91 | 2.27 | 61.09 |
| SUB | Rate as per Item No.3.7 of SH:MortarsRate as per item 3.7 | cum | 0.002 | 5,584.50 | 11.17 | |
| 0115 | LAB | Coolie | day | 0.056 | 736.00 | 41.22 |
| 0123 | LAB | Mason (brick layer) 1st classMason 1st class | day | 0.05 | 897.00 | 44.85 |
| 0114 | LAB | Beldar | day | 0.3 | 736.00 | 220.80 |
- TOTAL
- 570.97
- Add 1 % Water charges on “W-A”
- +3.79
- TOTAL
- 574.76
- Add GST on “X-A” (multiplying factor 0.2127)
- +81.45
- TOTAL
- 656.21
- Add 15% CPOH on “Y-A”
- +69.66
- TOTAL
- 725.87
- Add Cess @ 1% on “Z-A”
- +5.34
- Cost for 0.05 cum.
- 731.21
- Cost per cum.
- 14,624.20
- SAY
- ₹14,624.20
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 179
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 179. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.