Skip to main content
R/DAR 2023

Providing and fixing up to floor five level precast cement concrete solid block, including hoisting and setting in position with cement mortar 1:3 (1 cement : 3 coarse sand), cost of required centering, shuttering complete

1:1.5:3 (1 Cement: 1.5 coarse sand (zone-III) including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 25% : 3 graded stone aggregate 20 mm nominal size including (Recycled Concrete Aggregate (RCA) upto 25%)
Item number
4.7.1A
Analysis basis
250 no
Priced inputs
8
Derived rate
₹17,677.25/ NO
D-01/RATE ANALYSISITEM 4.7.1A

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.7.1A (Providing and fixing up to floor five level precast cement concrete solid block, including hoisting and setting in position with cement mortar 1:3 (1 cement : 3 coarse sand), cost of required centering, shuttering complete : 1:1.5:3 (1 Cement: 1.5 coarse sand (zone-III) including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 25% : 3 graded stone aggregate 20 mm nominal size including (Recycled Concrete Aggregate (RCA) upto 25%)) is derived from 8 priced inputs for 250 no and works out to ₹17,677.25 per no after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 250 no x 0.40m x 0.30m x 0.20m = 6 cum
  • Cement concrete 1:1.5:3
  • Centering and shuttering
  • (1) Mould
  • (i) Plate 3mm thick
  • 10x0.28 sqm. @ 23.55kg/m = 65.9 kg.
  • (ii) Flat 10x5mm
  • Handle ²
  • 10x2x0.25 x0.4 = 2kg. Total =67.9 kg
  • Assuming shuttering will become unserviceable
  • after use of 40 times and taking 75% credit.
  • Qty taken for cost of using once = 67.9x0.75/40
  • = 1.273 kg
  • (2) Moulding Platform
  • Assuming platform will become unserviceable
  • after use of 40 times.
  • (i) Brick on edge flooring cement mortar 1:6
  • 10x1x2.0x2.0m = 40 sqm.
  • Qty taken for cost of using once = 40/40 = 1
  • sqm
  • (ii) 25mm thick cement concrete 1:2:4 in pavement
  • 10x2.00x2.00x0.025 = 1
  • Qty taken for cost of using once = 1/40 = 0.025
  • cum
  • Mortar 1:3 for Fixing 10x0.202/100x25=0.51
  • Extra Labour for lifting (6x0.75x1.5=6.75)
  • Labour for hoisting and setting in position
ANALYSIS OF RATES · ITEM 4.7.1ADETAILS OF COST FOR 250 NO BLOCKS, 40X20X30CM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item No.4.1.2A of SH:Concrete WorkRate as per item 4.1.2Acum68,127.8048,766.80
SUBRate as per item no.10.1 SH: steel workRate as per item 10.1kg1.273117.35149.39
SUBRate as per item no. 11.1.2 SH.: Flooring work.Rate as per item 11.1.2sqm1965.55965.55
SUBRate as per item no. Sub AR-1 (Reference item no 11.7)Rate as per item Sub A/R-1cum0.0258,844.45221.11
SUBRate as per Item No 3.8Rate as per item 3.8cum0.514,881.952,489.79
0115LABCoolieday6.75736.004,968.00
0123LABMason (brick layer) 1st classMason 1st classday6897.005,382.00
0114LABBeldarday36736.0026,496.00
BUILD-UP TO RATE
TOTAL
89,438.64
Add 1 % Water charges on “W-A”
+393.36
TOTAL
89,832.00
Add GST on “X-A” (multiplying factor 0.2127)
+8,450.39
TOTAL
98,282.39
Add 15% CPOH on “Y-A”
+7,226.93
TOTAL
1,05,509.32
Add Cess @ 1% on “Z-A”
+554.06
Cost for 6 cum.
1,06,063.38
Cost per cum.
17,677.23
SAY
₹17,677.25
D-02/SOURCEPRINTED PAGE 177
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
177

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 177. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSCONCRETE WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.