CPWD Analysis of Rates · Concrete Work
Providing and fixing up to floor five level precast cement concrete hollow block, including hoisting and setting in position with cement mortar 1:3 (1 cement : 3 coarse sand), cost of required centering, shuttering complete
1:1.5:3 (1 Cement: 1.5 coarse sand (zone-III) ncluding manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 25% : 3 graded stone aggregate 20 mm nominal size including (Recycled Concrete Aggregate (RCA) upto 25%)
- Item number
- 4.8.1A
- Analysis basis
- Details of cost for one block of overall size
- Priced inputs
- 6
- Derived rate
- ₹14,526.20 / one block
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.8.1A — Providing and fixing up to floor five level precast cement concrete hollow block, including hoisting and setting in position with cement mortar 1:3 (1 cement : 3 coarse sand), cost of required centering, shuttering complete 1:1.5:3 (1 Cement: 1.5 coarse sand (zone-III) ncluding manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 25% : 3 graded stone aggregate 20 mm nominal size including (Recycled Concrete Aggregate (RCA) upto 25%) — is derived from 6 priced inputs for one block and works out to ₹14,526.20 per one block after water charges, GST, CPOH and cess. The full build-up is below.
- 1m x 0.50m and 0.10m thick having 6 vertical
- hollows, 40x20x30cm finished contents = 1mx0.5mx0.1m = 0.05cum
- Cement concrete 1:1.5:3
- Net qty = 0.05[6x0.5x{2x1/2(0.05+7)}x0.074] =
- 0.023cum
- Cement mortar 1:2 for fixing
- Extra Labour for lifting material upto floor V
- level
- Labour for hoisting and setting in position
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| Rate as per Item No.4.1.2A of SH:Concrete WorkRate as per item 4.1.2ASub-analysis | cum | 0.023 | 8,127.80 | 186.94 | |
| 9999 | Centering and shuttering including T&P charges, hire charges of steel mould, table vibrator, rammer, bolts nuts & washers etcMaterial | L.S. | 26.91 | 2.27 | 61.09 |
| Rate as per Item No.3.7 of SH:MortarsRate as per item 3.7Sub-analysis | cum | 0.002 | 5,584.50 | 11.17 | |
| 0115 | CoolieLabour | day | 0.056 | 736.00 | 41.22 |
| 0123 | Mason (brick layer) 1st classMason 1st classLabour | day | 0.05 | 897.00 | 44.85 |
| 0114 | BeldarLabour | day | 0.3 | 736.00 | 220.80 |
- TOTAL
- 566.07
- Add 1 % Water charges on “W-A”
- 3.79
- TOTAL
- 569.86
- Add GST on “X-A” (multiplying factor 0.2127)
- 81.45
- TOTAL
- 651.31
- Add 15% CPOH on “Y-A”
- 69.66
- TOTAL
- 720.97
- Add Cess @ 1% on “Z-A”
- 5.34
- Cost for 0.05 cum.
- 726.31
- Cost per cum.
- 14,526.20
- Say
- 14,526.20
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 179. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.