R/DAR 2023

Providing and fixing up to floor five level precast cement concrete hollow block, including hoisting and setting in position with cement mortar 1:3 (1 cement : 3 coarse sand), cost of required centering, shuttering complete

1:1.5:3 (1 Cement: 1.5 coarse sand (zone-III) ncluding manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 25% : 3 graded stone aggregate 20 mm nominal size including (Recycled Concrete Aggregate (RCA) upto 25%)
Item number
4.8.1A
Analysis basis
one block
Priced inputs
6
Derived rate
₹14,526.20/ ONE BLOCK
D-01/RATE ANALYSISITEM 4.8.1A

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.8.1A (Providing and fixing up to floor five level precast cement concrete hollow block, including hoisting and setting in position with cement mortar 1:3 (1 cement : 3 coarse sand), cost of required centering, shuttering complete 1:1.5:3 (1 Cement: 1.5 coarse sand (zone-III) ncluding manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 25% : 3 graded stone aggregate 20 mm nominal size including (Recycled Concrete Aggregate (RCA) upto 25%)) is derived from 6 priced inputs for one block and works out to ₹14,526.20 per one block after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 1m x 0.50m and 0.10m thick having 6 vertical
  • hollows, 40x20x30cm finished contents = 1mx0.5mx0.1m = 0.05cum
  • Cement concrete 1:1.5:3
  • Net qty = 0.05[6x0.5x{2x1/2(0.05+7)}x0.074] =
  • 0.023cum
  • Cement mortar 1:2 for fixing
  • Extra Labour for lifting material upto floor V
  • level
  • Labour for hoisting and setting in position
ANALYSIS OF RATES · ITEM 4.8.1ADETAILS OF COST FOR ONE BLOCK OF OVERALL SIZE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item No.4.1.2A of SH:Concrete WorkRate as per item 4.1.2Acum0.0238,127.80186.94
9999MATCentering and shuttering including T&P charges, hire charges of steel mould, table vibrator, rammer, bolts nuts & washers etcL.S.26.912.2761.09
SUBRate as per Item No.3.7 of SH:MortarsRate as per item 3.7cum0.0025,584.5011.17
0115LABCoolieday0.056736.0041.22
0123LABMason (brick layer) 1st classMason 1st classday0.05897.0044.85
0114LABBeldarday0.3736.00220.80
BUILD-UP TO RATE
TOTAL
566.07
Add 1 % Water charges on “W-A”
+3.79
TOTAL
569.86
Add GST on “X-A” (multiplying factor 0.2127)
+81.45
TOTAL
651.31
Add 15% CPOH on “Y-A”
+69.66
TOTAL
720.97
Add Cess @ 1% on “Z-A”
+5.34
Cost for 0.05 cum.
726.31
Cost per cum.
14,526.20
SAY
₹14,526.20
D-02/SOURCEPRINTED PAGE 179
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
179

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 179. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.