Providing and laying cement concrete in kerbs, steps and the like at or near ground level excluding the cost of centering, shuttering and finishing

1:1.5:3 (1 cement: 1.5 coarse sand (zone-III) including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 25% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 25%))

Item number
4.4.1A
Analysis basis
Details of cost for kerb :
Priced inputs
1
Derived rate
8,127.80

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.4.1A Providing and laying cement concrete in kerbs, steps and the like at or near ground level excluding the cost of centering, shuttering and finishing 1:1.5:3 (1 cement: 1.5 coarse sand (zone-III) including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 25% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 25%)) — is derived from 1 priced inputs and works out to ₹8,127.80 after water charges, GST, CPOH and cess. The full build-up is below.

  • 100m long 20cm deep and 30cm wide, 100m x
  • 0.30m x 0.20m = 6.00 cum.
  • Cement concrete 1:1.5:3
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per Item No.4.1.2A of SH:Concrete WorkRate as per item 4.1.2ASub-analysiscum68,127.8048,766.80
Cost for 6 cum.
48,766.80
Cost per cum.
8,127.80
Say
8,127.80

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 171. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.