Providing and laying cement concrete in kerbs, steps and the like at or near ground level excluding the cost of centering, shuttering and finishing

1:1.5:3 (1 cement: 1.5 coarse sand (zone-III) including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 25% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 25%))
Item number
4.4.1A
Analysis basis
Details of cost for kerb :
Priced inputs
1
Derived rate
₹8,127.80
D-01/RATE ANALYSISITEM 4.4.1A

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.4.1A (Providing and laying cement concrete in kerbs, steps and the like at or near ground level excluding the cost of centering, shuttering and finishing 1:1.5:3 (1 cement: 1.5 coarse sand (zone-III) including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 25% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 25%))) is derived from 1 priced inputs and works out to ₹8,127.80 after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 100m long 20cm deep and 30cm wide, 100m x
  • 0.30m x 0.20m = 6.00 cum.
  • Cement concrete 1:1.5:3
ANALYSIS OF RATES · ITEM 4.4.1ADETAILS OF COST FOR KERB :
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item No.4.1.2A of SH:Concrete WorkRate as per item 4.1.2Acum68,127.8048,766.80
BUILD-UP TO RATE
Cost for 6 cum.
48,766.80
Cost per cum.
8,127.80
SAY
₹8,127.80
D-02/SOURCEPRINTED PAGE 171
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
171

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 171. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.