Providing and fixing up to floor five level precast cement concrete string or lacing courses, copings, bed plates, anchor blocks, plain window sills, shelves, louvers, steps, stair cases, etc., including hoisting and setting in position with cement mortar 1:3 (1 Cement : 3 coarse sand), cost of required Centering complete
- Item number
- 4.5.1
- Analysis basis
- Plain window
- Priced inputs
- 6
- Derived rate
- ₹10,105.10/ PLAIN WINDOW
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.5.1 (Providing and fixing up to floor five level precast cement concrete string or lacing courses, copings, bed plates, anchor blocks, plain window sills, shelves, louvers, steps, stair cases, etc., including hoisting and setting in position with cement mortar 1:3 (1 Cement : 3 coarse sand), cost of required Centering complete 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20mm nominal size derived from natural sources)) is derived from 6 priced inputs for Plain window and works out to ₹10,105.10 per plain window after water charges, GST, CPOH and cess. The full build-up is below.
- 10x15x1m x 0.20m x 0.15m = 4.5cum.
- Cement concrete 1:1 :3
- (Extra labour for lifting = 0.75 x 4.5 x 1.5 = 5.1)
- Centering and shuttering
- (1) Mould
- (i) Plate 3mm thick
- [(2x1x0.15)+(2x0.15x0.20)]x10 = 3.6 sqm. @
- 23.55kg/m = 84.8 kg.
- (ii) Flat 10x5mm
- 10x4x1.0 = ² 40m
- 10x8x0.2 = 16m
- 10x4x0.15 = 6m
- Handle 10x2x0.25 = 5m
- 67m @ 0.4kg/m = 26.8 kg.
- Total = 111.6kg
- Assuming shuttering will become unserviceable
- after use of 40 times and taking 75% credit.
- Qty taken for cost of using once =
- 111.6x0.75/40 = 2.1 kg
- (2) Moulding Platform
- Assuming platform will become
- unserviceable after use of 40 times.
- (i) Brick on edge flooring cement mortar 1:6
- 10x1x2.0x2.0m = 40 sqm.
- Qty taken for cost of using once = 40/40 = 1
- sqm
- (ii) 25mm thick cement concrete 1:2:4 in pavement
- 10x2.00x2.00x0.025 = 1cum
- Qty taken for cost of using once = 1/40 = 0.025
- cum
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per Item No. 4.1.2 of SH: Concrete work ½Rate as per item 4.1.2 | cum | 4.5 | 8,340.85 | 37,533.83 | |
| 0115 | LAB | Coolie | day | 5.1 | 736.00 | 3,753.60 |
| SUB | Rate as per item No.10.1 SH: steel workRate as per item 10.1 | kg | 2.1 | 117.35 | 246.44 | |
| SUB | Rate as per item No. 11.1.2 of SH: Flooring workRate as per item 11.1.2 | sqm | 1 | 965.55 | 965.55 | |
| SUB | Rate as per Item No. 11.7 of S.H.: Flooring workRate as per item 11.7 | cum | 0.025 | 8,595.15 | 214.88 | |
| 9999 | MAT | Mortar and labour for hoisting and finishing | L.S. | 363 | 2.27 | 824.01 |
- TOTAL
- 43,538.31
- Add 1 % Water charges on “W-A”
- +45.78
- TOTAL
- 43,584.09
- Add GST on “X-A” (multiplying factor 0.2127)
- +983.40
- TOTAL
- 44,567.49
- Add 15% CPOH on “Y-A”
- +841.02
- TOTAL
- 45,408.51
- Add Cess @ 1% on “Z-A”
- +64.48
- Cost for 4.5 cum.
- 45,472.99
- Cost per cum.
- 10,105.11
- SAY
- ₹10,105.10
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 172
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 172. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.