CPWD Analysis of Rates · Concrete Work

Providing and fixing up to floor five level precast cement concrete string or lacing courses, copings, bed plates, anchor blocks, plain window sills, shelves, louvers, steps, stair cases, etc., including hoisting and setting in position with cement mortar 1:3 (1 Cement : 3 coarse sand), cost of required Centering complete

1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20mm nominal size derived from natural sources)

Item number
4.5.1
Analysis basis
Details of cost for Plain window sill 10x15 nos.
Priced inputs
6
Derived rate
10,105.10 / Plain window

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.5.1 Providing and fixing up to floor five level precast cement concrete string or lacing courses, copings, bed plates, anchor blocks, plain window sills, shelves, louvers, steps, stair cases, etc., including hoisting and setting in position with cement mortar 1:3 (1 Cement : 3 coarse sand), cost of required Centering complete 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20mm nominal size derived from natural sources) — is derived from 6 priced inputs for Plain window and works out to ₹10,105.10 per plain window after water charges, GST, CPOH and cess. The full build-up is below.

  • 10x15x1m x 0.20m x 0.15m = 4.5cum.
  • Cement concrete 1:1 :3
  • (Extra labour for lifting = 0.75 x 4.5 x 1.5 = 5.1)
  • Centering and shuttering
  • (1) Mould
  • (i) Plate 3mm thick
  • [(2x1x0.15)+(2x0.15x0.20)]x10 = 3.6 sqm. @
  • 23.55kg/m = 84.8 kg.
  • (ii) Flat 10x5mm
  • 10x4x1.0 = ² 40m
  • 10x8x0.2 = 16m
  • 10x4x0.15 = 6m
  • Handle 10x2x0.25 = 5m
  • 67m @ 0.4kg/m = 26.8 kg.
  • Total = 111.6kg
  • Assuming shuttering will become unserviceable
  • after use of 40 times and taking 75% credit.
  • Qty taken for cost of using once =
  • 111.6x0.75/40 = 2.1 kg
  • (2) Moulding Platform
  • Assuming platform will become
  • unserviceable after use of 40 times.
  • (i) Brick on edge flooring cement mortar 1:6
  • 10x1x2.0x2.0m = 40 sqm.
  • Qty taken for cost of using once = 40/40 = 1
  • sqm
  • (ii) 25mm thick cement concrete 1:2:4 in pavement
  • 10x2.00x2.00x0.025 = 1cum
  • Qty taken for cost of using once = 1/40 = 0.025
  • cum
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per Item No. 4.1.2 of SH: Concrete work ½Rate as per item 4.1.2Sub-analysiscum4.58,340.8537,533.83
0115CoolieLabourday5.1736.003,753.60
Rate as per item No.10.1 SH: steel workRate as per item 10.1Sub-analysiskg2.1117.35246.44
Rate as per item No. 11.1.2 of SH: Flooring workRate as per item 11.1.2Sub-analysissqm1965.55965.55
Rate as per Item No. 11.7 of S.H.: Flooring workRate as per item 11.7Sub-analysiscum0.0258,595.15214.88
9999Mortar and labour for hoisting and finishingMaterialL.S.3632.27824.01
TOTAL
43,538.31
Add 1 % Water charges on “W-A”
45.78
TOTAL
43,584.09
Add GST on “X-A” (multiplying factor 0.2127)
983.40
TOTAL
44,567.49
Add 15% CPOH on “Y-A”
841.02
TOTAL
45,408.51
Add Cess @ 1% on “Z-A”
64.48
Cost for 4.5 cum.
45,472.99
Cost per cum.
10,105.11
Say
10,105.10

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 172. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.