Skip to main content

CPWD Analysis of Rates · Concrete Work

Providing and laying cement concrete in kerbs, steps and the like at or near ground level excluding the cost of centering, shuttering and finishing

1:1½:3 (1 Cement: 1½ coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)

Item number
4.4.1
Analysis basis
Details of cost for kerb :
Priced inputs
1
Derived rate
8,340.85

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.4.1 Providing and laying cement concrete in kerbs, steps and the like at or near ground level excluding the cost of centering, shuttering and finishing 1:1½:3 (1 Cement: 1½ coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) — is derived from 1 priced inputs and works out to ₹8,340.85 after water charges, GST, CPOH and cess. The full build-up is below.

  • 100m long 20cm deep and 30cm wide, 100m x
  • 0.30m x 0.20m = 6.00 cum.
  • Cement concrete 1:1 :3
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per Item No.4.1.2 of SH:Concrete Work ½Rate as per item 4.1.2Sub-analysiscum68,340.8550,045.10
Cost for 6 cum.
50,045.10
Cost per cum.
8,340.85
Say
8,340.85

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 171. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works