Centering and shuttering including strutting, propping etc. and removal of form work for
- Item number
- 4.3.3
- Analysis basis
- 45 sqm
- Priced inputs
- 10
- Derived rate
- ₹961.30/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.3.3 (Centering and shuttering including strutting, propping etc. and removal of form work for : Columns, piers, abutments, pillars, posts and struts) is derived from 10 priced inputs for 45 sqm and works out to ₹961.30 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Size of column 450x450mm and 2.5m high
- Area of contact = 10x4x0.45x2.5 = 45 sqm.
- Assuming shuttering will become unserviceable
- after use of 40 times
- 25% of cost of material
- Qty taken for cost of using once =10x
- 8x0.85/40 = 1.70
- Qty taken for cost of using once =
- 10x4x0.85/40 = 0.85
- Qty taken for cost of using once =
- 10x5x0.85/40 = 1.063
- Qty taken for cost of using once =
- 10x4x0.85/40 = 0.85
- Qty taken for cost of using once =
- 10x1300x0.85/40 = 276.2
- Add maintenance charges @ 10% of cost of
- Less salvage value of material after full use @
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7331 | MAT | Wall form panel 1250x450 mm | each | 1.7 | 900.00 | 1,530.00 |
| 7332 | MAT | Corner angle 45x45x5 m 2.50 m longCorner angle 45x45x5 mm 2.50 m long | each | 0.85 | 275.00 | 233.75 |
| 7333 | MAT | Column clamp 450x1070 mColumn clamp 450x1070 mm | each | 1.063 | 1,020.00 | 1,084.26 |
| 7334 | MAT | Prop 2 m ( 2-3.5m)Prop 2 m ( 2-3.5 m) | each | 0.85 | 690.00 | 586.50 |
| 9999 | MAT | Assembly nut & bolt | L.S. | 276.2 | 2.27 | 626.97 |
| 9977 | MAT | Carriage | L.S. | 520 | 2.27 | 1,180.40 |
| 0116 | LAB | Fitter (grade 1) | day | 10 | 897.00 | 8,970.00 |
| 0114 | LAB | Beldar | day | 20 | 736.00 | 14,720.00 |
| 9999 | MAT | Shuttering oil | L.S. | 390 | 2.27 | 885.30 |
| 9977 | MAT | Carriage | L.S. | 260 | 2.27 | 590.20 |
- TOTAL
- 30,407.38
- Add 1 % Water charges on “W”
- +304.07
- TOTAL
- 30,711.45
- Add GST on “X” (multiplying factor 0.2127)
- +6,532.33
- TOTAL
- 37,243.78
- Add 15% CPOH on “Y”
- +5,586.57
- TOTAL
- 42,830.35
- Add Cess @ 1% on “Z”
- +428.30
- Cost for 45 sqm.
- 43,258.65
- Cost per sqm.
- 961.30
- SAY
- ₹961.30
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 170
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 170. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.