CPWD Analysis of Rates · Concrete Work
Centering and shuttering including strutting, propping etc. and removal of form work for
Columns, piers, abutments, pillars, posts and struts
- Item number
- 4.3.3
- Analysis basis
- Detail of cost for 45 sqm
- Priced inputs
- 10
- Derived rate
- ₹961.30 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.3.3 — Centering and shuttering including strutting, propping etc. and removal of form work for : Columns, piers, abutments, pillars, posts and struts — is derived from 10 priced inputs for 45 sqm and works out to ₹961.30 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Size of column 450x450mm and 2.5m high
- Area of contact = 10x4x0.45x2.5 = 45 sqm.
- Assuming shuttering will become unserviceable
- after use of 40 times
- 25% of cost of material
- Qty taken for cost of using once =10x
- 8x0.85/40 = 1.70
- Qty taken for cost of using once =
- 10x4x0.85/40 = 0.85
- Qty taken for cost of using once =
- 10x5x0.85/40 = 1.063
- Qty taken for cost of using once =
- 10x4x0.85/40 = 0.85
- Qty taken for cost of using once =
- 10x1300x0.85/40 = 276.2
- Add maintenance charges @ 10% of cost of
- Less salvage value of material after full use @
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7331 | Wall form panel 1250x450 mmMaterial | each | 1.7 | 900.00 | 1,530.00 |
| 7332 | Corner angle 45x45x5 m 2.50 m longCorner angle 45x45x5 mm 2.50 m longMaterial | each | 0.85 | 275.00 | 233.75 |
| 7333 | Column clamp 450x1070 mColumn clamp 450x1070 mmMaterial | each | 1.063 | 1,020.00 | 1,084.26 |
| 7334 | Prop 2 m ( 2-3.5m)Prop 2 m ( 2-3.5 m)Material | each | 0.85 | 690.00 | 586.50 |
| 9999 | Assembly nut & boltMaterial | L.S. | 276.2 | 2.27 | 626.97 |
| 9977 | CarriageMaterial | L.S. | 520 | 2.27 | 1,180.40 |
| 0116 | Fitter (grade 1)Labour | day | 10 | 897.00 | 8,970.00 |
| 0114 | BeldarLabour | day | 20 | 736.00 | 14,720.00 |
| 9999 | Shuttering oilMaterial | L.S. | 390 | 2.27 | 885.30 |
| 9977 | CarriageMaterial | L.S. | 260 | 2.27 | 590.20 |
- TOTAL
- 30,407.38
- Add 1 % Water charges on “W”
- 304.07
- TOTAL
- 30,711.45
- Add GST on “X” (multiplying factor 0.2127)
- 6,532.33
- TOTAL
- 37,243.78
- Add 15% CPOH on “Y”
- 5,586.57
- TOTAL
- 42,830.35
- Add Cess @ 1% on “Z”
- 428.30
- Cost for 45 sqm.
- 43,258.65
- Cost per sqm.
- 961.30
- Say
- 961.30
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 170. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works