Centering and shuttering including strutting, propping etc. and removal of form work for

Columns, piers, abutments, pillars, posts and struts
Item number
4.3.3
Analysis basis
45 sqm
Priced inputs
10
Derived rate
₹961.30/ SQM
D-01/RATE ANALYSISITEM 4.3.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.3.3 (Centering and shuttering including strutting, propping etc. and removal of form work for : Columns, piers, abutments, pillars, posts and struts) is derived from 10 priced inputs for 45 sqm and works out to ₹961.30 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Size of column 450x450mm and 2.5m high
  • Area of contact = 10x4x0.45x2.5 = 45 sqm.
  • Assuming shuttering will become unserviceable
  • after use of 40 times
  • 25% of cost of material
  • Qty taken for cost of using once =10x
  • 8x0.85/40 = 1.70
  • Qty taken for cost of using once =
  • 10x4x0.85/40 = 0.85
  • Qty taken for cost of using once =
  • 10x5x0.85/40 = 1.063
  • Qty taken for cost of using once =
  • 10x4x0.85/40 = 0.85
  • Qty taken for cost of using once =
  • 10x1300x0.85/40 = 276.2
  • Add maintenance charges @ 10% of cost of
  • Less salvage value of material after full use @
ANALYSIS OF RATES · ITEM 4.3.3DETAIL OF COST FOR 45 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7331MATWall form panel 1250x450 mmeach1.7900.001,530.00
7332MATCorner angle 45x45x5 m 2.50 m longCorner angle 45x45x5 mm 2.50 m longeach0.85275.00233.75
7333MATColumn clamp 450x1070 mColumn clamp 450x1070 mmeach1.0631,020.001,084.26
7334MATProp 2 m ( 2-3.5m)Prop 2 m ( 2-3.5 m)each0.85690.00586.50
9999MATAssembly nut & boltL.S.276.22.27626.97
9977MATCarriageL.S.5202.271,180.40
0116LABFitter (grade 1)day10897.008,970.00
0114LABBeldarday20736.0014,720.00
9999MATShuttering oilL.S.3902.27885.30
9977MATCarriageL.S.2602.27590.20
BUILD-UP TO RATE
TOTAL
30,407.38
Add 1 % Water charges on “W”
+304.07
TOTAL
30,711.45
Add GST on “X” (multiplying factor 0.2127)
+6,532.33
TOTAL
37,243.78
Add 15% CPOH on “Y”
+5,586.57
TOTAL
42,830.35
Add Cess @ 1% on “Z”
+428.30
Cost for 45 sqm.
43,258.65
Cost per sqm.
961.30
SAY
₹961.30
D-02/SOURCEPRINTED PAGE 170
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
170

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 170. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.