Centering and shuttering including strutting, propping etc. and removal of form work for
- Item number
- 4.3.2
- Priced inputs
- 11
- Derived rate
- ₹842.50
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.3.2 (Centering and shuttering including strutting, propping etc. and removal of form work for : Retaining walls, return walls, walls (any thickness) including attached pilasters, buttresses, plinth and string courses fillets, kerbs and steps etc) is derived from 11 priced inputs and works out to ₹842.50 after water charges, GST, CPOH and cess. The full build-up is below.
- Details for 7.5 m long and 1.00 m high wall
- Area of contact 2x7.5x1.0 = 15.00 sqm.
- Assuming shuttering material will become
- unserviceable after use of 40 times
- Adding for maintenance @ 10% of cost
- Taking salvage value after full use of material
- @ 25% of cost
- Qty taken for cost of using once =24x0.85/40
- = 0.51
- Qty taken for cost of using once =6x0.85/40 =
- 0.13
- Qty taken for cost of using once =24x0.85/40
- = 0.51
- Qty taken for cost of using once =12x0.85/40 =
- 0.255
- Qty taken for cost of using once =32x0.85/40
- = 0.68
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7319 | MAT | Wall form panel 1250x500 mm | each | 0.51 | 900.00 | 459.00 |
| 7327 | MAT | 100 mm channel shoulder 2.5 m long | each | 0.13 | 950.00 | 123.50 |
| 7328 | MAT | Double clip ( bridge clip)Double clip (bridge clip) | each | 0.51 | 80.00 | 40.80 |
| 7329 | MAT | Single clip | each | 0.255 | 64.00 | 16.32 |
| 7330 | MAT | M.S. tube 40 mm dia | metre | 0.68 | 225.00 | 153.00 |
| 9999 | MAT | Nut & Bolts | L.S. | 27.62 | 2.27 | 62.70 |
| 9977 | MAT | Carriage | L.S. | 78 | 2.27 | 177.06 |
| 0116 | LAB | Fitter (grade 1) | day | 3.5 | 897.00 | 3,139.50 |
| 0114 | LAB | Beldar | day | 6 | 736.00 | 4,416.00 |
| 9999 | MAT | Shuttering oil | L.S. | 78 | 2.27 | 177.06 |
| 9999 | MAT | Sundries | L.S. | 52 | 2.27 | 118.04 |
- TOTAL
- 8,882.98
- Add 1 % Water charges on “W”
- +88.83
- TOTAL
- 8,971.81
- Add GST on “X” (multiplying factor 0.2127)
- +1,908.30
- TOTAL
- 10,880.11
- Add 15% CPOH on “Y”
- +1,632.02
- TOTAL
- 12,512.13
- Add Cess @ 1% on “Z”
- +125.12
- Cost for 15.00sqm.
- 12,637.25
- Cost per sqm.
- 842.48
- SAY
- ₹842.50
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 169
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 169. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.