Centering and shuttering including strutting, propping etc. and removal of form work for

Retaining walls, return walls, walls (any thickness) including attached pilasters, buttresses, plinth and string courses fillets, kerbs and steps etc
Item number
4.3.2
Priced inputs
11
Derived rate
₹842.50
D-01/RATE ANALYSISITEM 4.3.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.3.2 (Centering and shuttering including strutting, propping etc. and removal of form work for : Retaining walls, return walls, walls (any thickness) including attached pilasters, buttresses, plinth and string courses fillets, kerbs and steps etc) is derived from 11 priced inputs and works out to ₹842.50 after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Details for 7.5 m long and 1.00 m high wall
  • Area of contact 2x7.5x1.0 = 15.00 sqm.
  • Assuming shuttering material will become
  • unserviceable after use of 40 times
  • Adding for maintenance @ 10% of cost
  • Taking salvage value after full use of material
  • @ 25% of cost
  • Qty taken for cost of using once =24x0.85/40
  • = 0.51
  • Qty taken for cost of using once =6x0.85/40 =
  • 0.13
  • Qty taken for cost of using once =24x0.85/40
  • = 0.51
  • Qty taken for cost of using once =12x0.85/40 =
  • 0.255
  • Qty taken for cost of using once =32x0.85/40
  • = 0.68
ANALYSIS OF RATES · ITEM 4.3.2
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7319MATWall form panel 1250x500 mmeach0.51900.00459.00
7327MAT100 mm channel shoulder 2.5 m longeach0.13950.00123.50
7328MATDouble clip ( bridge clip)Double clip (bridge clip)each0.5180.0040.80
7329MATSingle clipeach0.25564.0016.32
7330MATM.S. tube 40 mm diametre0.68225.00153.00
9999MATNut & BoltsL.S.27.622.2762.70
9977MATCarriageL.S.782.27177.06
0116LABFitter (grade 1)day3.5897.003,139.50
0114LABBeldarday6736.004,416.00
9999MATShuttering oilL.S.782.27177.06
9999MATSundriesL.S.522.27118.04
BUILD-UP TO RATE
TOTAL
8,882.98
Add 1 % Water charges on “W”
+88.83
TOTAL
8,971.81
Add GST on “X” (multiplying factor 0.2127)
+1,908.30
TOTAL
10,880.11
Add 15% CPOH on “Y”
+1,632.02
TOTAL
12,512.13
Add Cess @ 1% on “Z”
+125.12
Cost for 15.00sqm.
12,637.25
Cost per sqm.
842.48
SAY
₹842.50
D-02/SOURCEPRINTED PAGE 169
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
169

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 169. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSCONCRETE WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.