Skip to main content

CPWD Analysis of Rates · Concrete Work

Centering and shuttering including strutting, propping etc. and removal of form work for

Retaining walls, return walls, walls (any thickness) including attached pilasters, buttresses, plinth and string courses fillets, kerbs and steps etc

Item number
4.3.2
Priced inputs
11
Derived rate
842.50

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.3.2 Centering and shuttering including strutting, propping etc. and removal of form work for : Retaining walls, return walls, walls (any thickness) including attached pilasters, buttresses, plinth and string courses fillets, kerbs and steps etc — is derived from 11 priced inputs and works out to ₹842.50 after water charges, GST, CPOH and cess. The full build-up is below.

  • Details for 7.5 m long and 1.00 m high wall
  • Area of contact 2x7.5x1.0 = 15.00 sqm.
  • Assuming shuttering material will become
  • unserviceable after use of 40 times
  • Adding for maintenance @ 10% of cost
  • Taking salvage value after full use of material
  • @ 25% of cost
  • Qty taken for cost of using once =24x0.85/40
  • = 0.51
  • Qty taken for cost of using once =6x0.85/40 =
  • 0.13
  • Qty taken for cost of using once =24x0.85/40
  • = 0.51
  • Qty taken for cost of using once =12x0.85/40 =
  • 0.255
  • Qty taken for cost of using once =32x0.85/40
  • = 0.68
CodeInputUnitQuantityRate (INR)Amount (INR)
7319Wall form panel 1250x500 mmMaterialeach0.51900.00459.00
7327100 mm channel shoulder 2.5 m longMaterialeach0.13950.00123.50
7328Double clip ( bridge clip)Double clip (bridge clip)Materialeach0.5180.0040.80
7329Single clipMaterialeach0.25564.0016.32
7330M.S. tube 40 mm diaMaterialmetre0.68225.00153.00
9999Nut & BoltsMaterialL.S.27.622.2762.70
9977CarriageMaterialL.S.782.27177.06
0116Fitter (grade 1)Labourday3.5897.003,139.50
0114BeldarLabourday6736.004,416.00
9999Shuttering oilMaterialL.S.782.27177.06
9999SundriesMaterialL.S.522.27118.04
TOTAL
8,882.98
Add 1 % Water charges on “W”
88.83
TOTAL
8,971.81
Add GST on “X” (multiplying factor 0.2127)
1,908.30
TOTAL
10,880.11
Add 15% CPOH on “Y”
1,632.02
TOTAL
12,512.13
Add Cess @ 1% on “Z”
125.12
Cost for 15.00sqm.
12,637.25
Cost per sqm.
842.48
Say
842.50

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 169. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works