Centering and shuttering including strutting, propping etc. and removal of form work for
- Item number
- 4.3.1
- Analysis basis
- footing size
- Priced inputs
- 12
- Derived rate
- ₹392.15/ FOOTING SIZE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.3.1 (Centering and shuttering including strutting, propping etc. and removal of form work for : Foundations, footings, bases for columns) is derived from 12 priced inputs for footing size and works out to ₹392.15 per footing size after water charges, GST, CPOH and cess. The full build-up is below.
- 1.00m
- Contact area = 10.00 sqm.
- Assuming shuttering material will become
- unserviceable after use of 40 times, Adding for
- maintenance @ 10% of cost, Taking salvage
- value after full use of material @ 25% of cost
- Qty taken for cost of using once =16x0.85/40
- = 0.34
- Qty taken for cost of using once =4x0.85/40 =
- 0.085
- Qty taken for cost of using once =8x0.85/40=
- 0.17
- Qty taken for cost of using once =16x0.85/40
- = 0.34
- Qty taken for cost of using once =8x0.85/40 =
- 0.17
- Qty taken for cost of using once
- =10.00x0.85/40 = 0.213
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7319 | MAT | Wall form panel 1250x500 mm | each | 0.34 | 900.00 | 306.00 |
| 7326 | MAT | Corner angle 45x45x5 mm 1.50 m long | each | 0.085 | 257.00 | 21.85 |
| 7327 | MAT | 100 mm channel shoulder 2.5 m long | each | 0.17 | 950.00 | 161.50 |
| 7328 | MAT | Double clip ( bridge clip)Double clip (bridge clip) | each | 0.34 | 80.00 | 27.20 |
| 7329 | MAT | Single clip | each | 0.17 | 64.00 | 10.88 |
| 7330 | MAT | M.S. tube 40 mm dia | metre | 0.213 | 225.00 | 47.93 |
| 9999 | MAT | Assembly nuts & bolts | L.S. | 22.1 | 2.27 | 50.17 |
| 9977 | MAT | Carriage | L.S. | 78 | 2.27 | 177.06 |
| 0116 | LAB | Fitter (grade 1) | day | 0.75 | 897.00 | 672.75 |
| 0114 | LAB | Beldar | day | 1.5 | 736.00 | 1,104.00 |
| 9999 | MAT | Shuttering oil | L.S. | 52 | 2.27 | 118.04 |
| 9999 | MAT | Sundries | L.S. | 26 | 2.27 | 59.02 |
- TOTAL
- 2,756.40
- Add 1 % Water charges on “W”
- +27.56
- TOTAL
- 2,783.96
- Add GST on “X” (multiplying factor 0.2127)
- +592.15
- TOTAL
- 3,376.11
- Add 15% CPOH on “Y”
- +506.42
- TOTAL
- 3,882.53
- Add Cess @ 1% on “Z”
- +38.83
- Cost for 10.00 sqm
- 3,921.36
- Cost per sqm.
- 392.14
- SAY
- ₹392.15
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 168
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 168. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.