CPWD Analysis of Rates · Concrete Work

Centering and shuttering including strutting, propping etc. and removal of form work for

Foundations, footings, bases for columns

Item number
4.3.1
Analysis basis
Details of cost for footing size 2.50mx2.50mx-
Priced inputs
12
Derived rate
392.15 / footing size

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.3.1 Centering and shuttering including strutting, propping etc. and removal of form work for : Foundations, footings, bases for columns — is derived from 12 priced inputs for footing size and works out to ₹392.15 per footing size after water charges, GST, CPOH and cess. The full build-up is below.

  • 1.00m
  • Contact area = 10.00 sqm.
  • Assuming shuttering material will become
  • unserviceable after use of 40 times, Adding for
  • maintenance @ 10% of cost, Taking salvage
  • value after full use of material @ 25% of cost
  • Qty taken for cost of using once =16x0.85/40
  • = 0.34
  • Qty taken for cost of using once =4x0.85/40 =
  • 0.085
  • Qty taken for cost of using once =8x0.85/40=
  • 0.17
  • Qty taken for cost of using once =16x0.85/40
  • = 0.34
  • Qty taken for cost of using once =8x0.85/40 =
  • 0.17
  • Qty taken for cost of using once
  • =10.00x0.85/40 = 0.213
CodeInputUnitQuantityRate (INR)Amount (INR)
7319Wall form panel 1250x500 mmMaterialeach0.34900.00306.00
7326Corner angle 45x45x5 mm 1.50 m longMaterialeach0.085257.0021.85
7327100 mm channel shoulder 2.5 m longMaterialeach0.17950.00161.50
7328Double clip ( bridge clip)Double clip (bridge clip)Materialeach0.3480.0027.20
7329Single clipMaterialeach0.1764.0010.88
7330M.S. tube 40 mm diaMaterialmetre0.213225.0047.93
9999Assembly nuts & boltsMaterialL.S.22.12.2750.17
9977CarriageMaterialL.S.782.27177.06
0116Fitter (grade 1)Labourday0.75897.00672.75
0114BeldarLabourday1.5736.001,104.00
9999Shuttering oilMaterialL.S.522.27118.04
9999SundriesMaterialL.S.262.2759.02
TOTAL
2,756.40
Add 1 % Water charges on “W”
27.56
TOTAL
2,783.96
Add GST on “X” (multiplying factor 0.2127)
592.15
TOTAL
3,376.11
Add 15% CPOH on “Y”
506.42
TOTAL
3,882.53
Add Cess @ 1% on “Z”
38.83
Cost for 10.00 sqm
3,921.36
Cost per sqm.
392.14
Say
392.15

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 168. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.