R/DAR 2023

Centering and shuttering including strutting, propping etc. and removal of form work for

Foundations, footings, bases for columns
Item number
4.3.1
Analysis basis
footing size
Priced inputs
12
Derived rate
₹392.15/ FOOTING SIZE
D-01/RATE ANALYSISITEM 4.3.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.3.1 (Centering and shuttering including strutting, propping etc. and removal of form work for : Foundations, footings, bases for columns) is derived from 12 priced inputs for footing size and works out to ₹392.15 per footing size after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 1.00m
  • Contact area = 10.00 sqm.
  • Assuming shuttering material will become
  • unserviceable after use of 40 times, Adding for
  • maintenance @ 10% of cost, Taking salvage
  • value after full use of material @ 25% of cost
  • Qty taken for cost of using once =16x0.85/40
  • = 0.34
  • Qty taken for cost of using once =4x0.85/40 =
  • 0.085
  • Qty taken for cost of using once =8x0.85/40=
  • 0.17
  • Qty taken for cost of using once =16x0.85/40
  • = 0.34
  • Qty taken for cost of using once =8x0.85/40 =
  • 0.17
  • Qty taken for cost of using once
  • =10.00x0.85/40 = 0.213
ANALYSIS OF RATES · ITEM 4.3.1DETAILS OF COST FOR FOOTING SIZE 2.50MX2.50MX-
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7319MATWall form panel 1250x500 mmeach0.34900.00306.00
7326MATCorner angle 45x45x5 mm 1.50 m longeach0.085257.0021.85
7327MAT100 mm channel shoulder 2.5 m longeach0.17950.00161.50
7328MATDouble clip ( bridge clip)Double clip (bridge clip)each0.3480.0027.20
7329MATSingle clipeach0.1764.0010.88
7330MATM.S. tube 40 mm diametre0.213225.0047.93
9999MATAssembly nuts & boltsL.S.22.12.2750.17
9977MATCarriageL.S.782.27177.06
0116LABFitter (grade 1)day0.75897.00672.75
0114LABBeldarday1.5736.001,104.00
9999MATShuttering oilL.S.522.27118.04
9999MATSundriesL.S.262.2759.02
BUILD-UP TO RATE
TOTAL
2,756.40
Add 1 % Water charges on “W”
+27.56
TOTAL
2,783.96
Add GST on “X” (multiplying factor 0.2127)
+592.15
TOTAL
3,376.11
Add 15% CPOH on “Y”
+506.42
TOTAL
3,882.53
Add Cess @ 1% on “Z”
+38.83
Cost for 10.00 sqm
3,921.36
Cost per sqm.
392.14
SAY
₹392.15
D-02/SOURCEPRINTED PAGE 168
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
168

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 168. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.