Making plinth protection 50mm thick of cement concrete 1:3:6 (1 cement : 3 manufactured sand derived from Recycled Concrete Aggregate (RCA) : 6 graded stone aggregate 20 mm nominal size Recycled Concrete Aggregate (RCA) over 75mm thick bed of dry brick ballast 40 mm nominal size, well rammed and consolidated and grouted with fine sand, including necessary excavation, levelling & dressing & finishing the top smooth

Item number
4.17A
Analysis basis
10 sqm
Priced inputs
16
Derived rate
₹702.30/ SQM
D-01/RATE ANALYSISITEM 4.17A

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.17A (Making plinth protection 50mm thick of cement concrete 1:3:6 (1 cement : 3 manufactured sand derived from Recycled Concrete Aggregate (RCA) : 6 graded stone aggregate 20 mm nominal size Recycled Concrete Aggregate (RCA) over 75mm thick bed of dry brick ballast 40 mm nominal size, well rammed and consolidated and grouted with fine sand, including necessary excavation, levelling & dressing & finishing the top smooth) is derived from 16 priced inputs for 10 sqm and works out to ₹702.30 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Qty. of cement concrete 1:3:6 on 10 sqm. area
  • = 0.5 cum.
ANALYSIS OF RATES · ITEM 4.17ADETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0287MATBrick Aggregate (Single size) : 40 mm nominal sizecum0.75700.00525.00
0983MATFine sand (zone IV)cum0.06980.0058.80
0114LABBeldarday0.16736.00117.76
0115LABCoolieday0.11736.0080.96
0279MATRecycled Concrete Aggregate (RCA) 20 mm nominal sizecum0.35957.00334.95
0281MATRecycled Concrete Aggregate (RCA) 10 mm nominal sizecum0.12957.00114.84
0278MATManufactured sand derived from Recycled Concrete Aggregate (RCA)cum0.23957.00220.11
0367MATPortland CementPortland Cement (OPC-43 Grade)tonne0.115,156.00567.16
0114LABBeldarday1736.00736.00
0123LABMason (brick layer) 1st classMason 1st classday0.05897.0044.85
0101LABBhistiday0.33816.00269.28
9999MATHire and runing charges of mechanical mixerL.S.13.392.2730.40
9999MATSundriesL.S.6.762.2715.35
0155LABMason (average)day0.27857.00231.39
0114LABBeldarday1.08736.00794.88
0115LABCoolieday1.08736.00794.88
BUILD-UP TO RATE
TOTAL
4,936.61
Add 1 % Water charges on “W”
+49.37
TOTAL
4,985.98
Add GST on “X” (multiplying factor 0.2127)
+1,060.52
TOTAL
6,046.50
Add 15% CPOH on “Y”
+906.98
TOTAL
6,953.48
Add Cess @ 1% on “Z”
+69.53
Cost of 10.00 sqm
7,023.01
Cost of 1.00 sqm
702.30
SAY
₹702.30
D-02/SOURCEPRINTED PAGE 188
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
188

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 188. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSCONCRETE WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.