CPWD Analysis of Rates · Concrete Work

Making plinth protection 50mm thick of cement concrete 1:3:6 (1 cement : 3 coarse sand (zoneIII) derived from natural sources : 6 graded stone aggregate 20 mm nominal size derived from natural sources) over 75mm thick bed of dry brick ballast 40 mm nominal size, well rammed and consolidated and grouted with fine sand, including necessary excavation, levelling & dressing & finishing the top smooth

Item number
4.17
Analysis basis
Detail of cost for 10 sqm
Priced inputs
16
Derived rate
749.30 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.17 Making plinth protection 50mm thick of cement concrete 1:3:6 (1 cement : 3 coarse sand (zoneIII) derived from natural sources : 6 graded stone aggregate 20 mm nominal size derived from natural sources) over 75mm thick bed of dry brick ballast 40 mm nominal size, well rammed and consolidated and grouted with fine sand, including necessary excavation, levelling & dressing & finishing the top smooth — is derived from 16 priced inputs for 10 sqm and works out to ₹749.30 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Qty. of cement concrete 1:3:6 on 10 sqm. area
  • = 0.5 cum.
CodeInputUnitQuantityRate (INR)Amount (INR)
0287Brick Aggregate (Single size) : 40 mm nominal sizeMaterialcum0.75700.00525.00
0983Fine sand (zone IV)Materialcum0.06980.0058.80
0114BeldarLabourday0.16736.00117.76
0115CoolieLabourday0.11736.0080.96
0295Stone Aggregate (Single size) : 20 mm nominal sizeMaterialcum0.351,425.00498.75
0297Stone Aggregate (Single size) : 10 mm nominal sizeMaterialcum0.121,400.00168.00
0982Coarse sand (zone III)Materialcum0.231,450.00333.50
0367Portland CementPortland Cement (OPC-43 Grade)Materialtonne0.115,156.00567.16
0114BeldarLabourday1736.00736.00
0123Mason (brick layer) 1st classMason 1st classLabourday0.05897.0044.85
0101BhistiLabourday0.33816.00269.28
9999Hire and runing charges of mechanical mixerMaterialL.S.13.392.2730.40
9999SundriesMaterialL.S.6.762.2715.35
0155Mason (average)Labourday0.27857.00231.39
0114BeldarLabourday1.08736.00794.88
0115CoolieLabourday1.08736.00794.88
TOTAL
5,266.96
Add 1 % Water charges on “W”
52.67
TOTAL
5,319.63
Add GST on “X” (multiplying factor 0.2127)
1,131.49
TOTAL
6,451.12
Add 15% CPOH on “Y”
967.67
TOTAL
7,418.79
Add Cess @ 1% on “Z”
74.19
Cost of 10.00 sqm
7,492.98
Cost of 1.00 sqm
749.30
Say
749.30

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 187. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.