Extra for laying concrete in or under foul positions
- Item number
- 4.16
- Analysis basis
- 1 cum
- Priced inputs
- 4
- Derived rate
- ₹467.55/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.16 (Extra for laying concrete in or under foul positions) is derived from 4 priced inputs for 1 cum and works out to ₹467.55 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- Extra labour due to slow progress-
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0123 | LAB | Mason (brick layer) 1st classMason 1st class | day | 0.02 | 897.00 | 17.94 |
| 0124 | LAB | Mason (brick layer) 2nd classMason 2nd class | day | 0.02 | 816.00 | 16.32 |
| 0114 | LAB | Beldar | day | 0.25 | 736.00 | 184.00 |
| 0115 | LAB | Coolie | day | 0.15 | 736.00 | 110.40 |
- TOTAL
- 328.66
- Add 1 % Water charges on “W”
- +3.29
- TOTAL
- 331.95
- Add GST on “X” (multiplying factor 0.2127)
- +70.61
- TOTAL
- 402.56
- Add 15% CPOH on “Y”
- +60.38
- TOTAL
- 462.94
- Add Cess @ 1% on “Z”
- +4.63
- Cost for 1 cum.
- 467.57
- SAY
- ₹467.55
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 187
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 187. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.