R/DAR 2023

Extra for laying concrete in or under foul positions

Item number
4.16
Analysis basis
1 cum
Priced inputs
4
Derived rate
₹467.55/ CUM
D-01/RATE ANALYSISITEM 4.16

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.16 (Extra for laying concrete in or under foul positions) is derived from 4 priced inputs for 1 cum and works out to ₹467.55 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Extra labour due to slow progress-
ANALYSIS OF RATES · ITEM 4.16DETAILS OF COST FOR 1 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0123LABMason (brick layer) 1st classMason 1st classday0.02897.0017.94
0124LABMason (brick layer) 2nd classMason 2nd classday0.02816.0016.32
0114LABBeldarday0.25736.00184.00
0115LABCoolieday0.15736.00110.40
BUILD-UP TO RATE
TOTAL
328.66
Add 1 % Water charges on “W”
+3.29
TOTAL
331.95
Add GST on “X” (multiplying factor 0.2127)
+70.61
TOTAL
402.56
Add 15% CPOH on “Y”
+60.38
TOTAL
462.94
Add Cess @ 1% on “Z”
+4.63
Cost for 1 cum.
467.57
SAY
₹467.55
D-02/SOURCEPRINTED PAGE 187
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
187

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 187. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.