CPWD Analysis of Rates · Concrete Work
Extra for laying concrete in or under water and/or liquid mud including cost of pumping or bailing out water and removing slush etc. complete
- Item number
- 4.15
- Analysis basis
- Details of cost for 4.2 cum per 1 m depth (14
- Priced inputs
- 2
- Derived rate
- ₹1,098.80 / cum
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.15 — Extra for laying concrete in or under water and/or liquid mud including cost of pumping or bailing out water and removing slush etc. complete — is derived from 2 priced inputs for 4.2 cum and works out to ₹1,098.80 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- cum per 0.3m depth)
- Quantity of concrete = 14 cum. pumping hours
- = 3 hrs. or 0.375 day.
- for cleaning slush
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0011 | Hire charges of Pumpset of capacity 4000 litres/hourHire charges of Pump set of capacity 4000 litres/hourMachinery | day | 0.375 | 800.00 | 300.00 |
| 0114 | BeldarLabour | day | 4 | 736.00 | 2,944.00 |
- TOTAL
- 3,244.00
- Add 1 % Water charges on “W”
- 32.44
- TOTAL
- 3,276.44
- Add GST on “X” (multiplying factor 0.2127)
- 696.90
- TOTAL
- 3,973.34
- Add 15% CPOH on “Y”
- 596.00
- TOTAL
- 4,569.34
- Add Cess @ 1% on “Z”
- 45.69
- Cost of 4.2cum per 1 metre depth
- 4,615.03
- Cost of cum per metre depth
- 1,098.82
- Say
- 1,098.80
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 187. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.