Extra for concrete work in superstructure above floor V level for each four floors or part thereof by mechnical means
- Item number
- 4.14
- Analysis basis
- 5.3 cum
- Priced inputs
- 1
- Derived rate
- ₹169.45/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.14 (Extra for concrete work in superstructure above floor V level for each four floors or part thereof by mechnical means) is derived from 1 priced inputs for 5.3 cum and works out to ₹169.45 per cum after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0037 | MACH | Mobile crane | day | 0.125 | 5,050.00 | 631.25 |
- TOTAL
- 631.25
- Add 1 % Water charges on “W”
- +6.31
- TOTAL
- 637.56
- Add GST on “X” (multiplying factor 0.2127)
- +135.61
- TOTAL
- 773.17
- Add 15% CPOH on “Y”
- +115.98
- TOTAL
- 889.15
- Add Cess @ 1% on “Z”
- +8.89
- Cost of 5.3 Cum.
- 898.04
- Cost for 1 cum
- 169.44
- SAY
- ₹169.45
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 186
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 186. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.