CPWD Analysis of Rates · Concrete Work
Providing & applying a coat of residual petroleum bitumen of grade of VG-10 of approved quality using 1.7 kg per square metre on damp proof course after cleaning the surface with brushes and finally with a piece of cloth lightly soaked in kerosene oil
- Item number
- 4.13
- Analysis basis
- Details of cost for 10sqm.
- Priced inputs
- 7
- Derived rate
- ₹146.15 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.13 — Providing & applying a coat of residual petroleum bitumen of grade of VG-10 of approved quality using 1.7 kg per square metre on damp proof course after cleaning the surface with brushes and finally with a piece of cloth lightly soaked in kerosene oil — is derived from 7 priced inputs and works out to ₹146.15 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Fuel for heating
- Heating the material
- Spreading hot tar over damp proof course
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0309 | Paving bitumen VG-10 of approved qualityPaving bitumen of grade VG-10 of approved qualityMaterial | tonne | 0.017 | 33,530.00 | 570.01 |
| 0771 | Kerosene oilMaterial | litre | 1.23 | 50.00 | 61.50 |
| 0370 | Coal (steam)Material | quintal | 0.035 | 500.00 | 17.50 |
| 0114 | BeldarLabour | day | 0.12 | 736.00 | 88.32 |
| 0115 | CoolieLabour | day | 0.07 | 736.00 | 51.52 |
| 0131 | PainterLabour | day | 0.2 | 816.00 | 163.20 |
| 9988 | Sundries (Carriage of kerosene, steam coal, brushes, T&P etc.)Material | L.S. | 33.15 | 2.27 | 75.25 |
- TOTAL
- 1,027.30
- Add 1 % Water charges on “W”
- 10.27
- TOTAL
- 1,037.57
- Add GST on “X” (multiplying factor 0.2127)
- 220.69
- TOTAL
- 1,258.26
- Add 15% CPOH on “Y”
- 188.74
- TOTAL
- 1,447.00
- Add Cess @ 1% on “Z”
- 14.47
- Cost for 10 sqm.
- 1,461.47
- Cost of 1 sqm.
- 146.15
- Say
- 146.15
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 186. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.