Extra for providing and mixing water proofing material in cement concrete work in doses by weight of cement as per manufacturer’s specification

Item number
4.12
Analysis basis
per bag
Priced inputs
2
Derived rate
₹18.15/ PER BAG
D-01/RATE ANALYSISITEM 4.12

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.12 (Extra for providing and mixing water proofing material in cement concrete work in doses by weight of cement as per manufacturer’s specification) is derived from 2 priced inputs for per bag and works out to ₹18.15 per per bag after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Approved waterproofing’materials according
  • to the recommended proportions@0.20% of
  • cement
ANALYSIS OF RATES · ITEM 4.12DETAILS OF COST FOR PER BAG OF 50KG. OF CEMENT
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1213MATWater proofing materialskilogram0.145.004.50
9988MATCarriage of water proofing material and labour for mixing etcL.S.3.642.278.26
BUILD-UP TO RATE
TOTAL
12.76
Add 1 % Water charges on “W”
+0.13
TOTAL
12.89
Add GST on “X” (multiplying factor 0.2127)
+2.74
TOTAL
15.63
Add 15% CPOH on “Y”
+2.34
TOTAL
17.97
Add Cess @ 1% on “Z”
+0.18
Cost per bag of cement of 50kg.
18.15
SAY
₹18.15
D-02/SOURCEPRINTED PAGE 185
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
185

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 185. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.