CPWD Analysis of Rates · Concrete Work
Providing and laying damp-proof course 50mm thick with cement concrete 1:2:4 (1 cement : 2 coarse sand (zone-III) ncluding manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 25% : 4 graded stone aggregate 20mm nominal size (Recycled Concrete Aggregate (RCA) upto 25%)
- Item number
- 4.11A
- Analysis basis
- Details of cost for 10 sqm
- Priced inputs
- 4
- Derived rate
- ₹484.60 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.11A — Providing and laying damp-proof course 50mm thick with cement concrete 1:2:4 (1 cement : 2 coarse sand (zone-III) ncluding manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 25% : 4 graded stone aggregate 20mm nominal size (Recycled Concrete Aggregate (RCA) upto 25%) — is derived from 4 priced inputs for 10 sqm and works out to ₹484.60 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- 1:2:4 (1 cement : 2 coarse sand (zone-III)
- Recycled concrete aggregate (RCA) upto 25%
- : 4 graded stone aggregate 20mm nominal size
- (Recycled Concrete Aggregate (RCA) upto
- 25%)) = 10x0.05 = 0.50 cum
- Add for delay :
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| Rate as per item no 4.1.3A of SH:Concrete workRate as per item 4.1.3ASub-analysis | cum | 0.5 | 7,654.85 | 3,827.43 | |
| 0123 | Mason (brick layer) 1st classMason 1st classLabour | day | 0.4 | 897.00 | 358.80 |
| 0124 | Mason (brick layer) 2nd classMason 2nd classLabour | day | 0.4 | 816.00 | 326.40 |
| 9999 | Sundries (Form work etc.)Material | L.S. | 13.52 | 2.27 | 30.69 |
- TOTAL
- 4,543.32
- Add 1 % Water charges on “W-A”
- 7.16
- TOTAL
- 4,550.48
- Add GST on “X-A” (multiplying factor 0.2127)
- 153.79
- TOTAL
- 4,704.27
- Add 15% CPOH on “Y-A”
- 131.53
- TOTAL
- 4,835.80
- Add Cess @ 1% on “Z-A”
- 10.08
- Cost for 10 sqm.
- 4,845.88
- Cost of 1 sqm.
- 484.59
- Say
- 484.60
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 185. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.