CPWD Analysis of Rates · Concrete Work

Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level

1:5:10 (1 cement : 5 coarse sand (zone-III) derived from natural sources : 10 graded stone aggregate 40 mm nominal size derived from natural sources)

Item number
4.1.10
Analysis basis
Details of cost for 1 cum.
Priced inputs
10
Derived rate
6,518.60 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.1.10 Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:5:10 (1 cement : 5 coarse sand (zone-III) derived from natural sources : 10 graded stone aggregate 40 mm nominal size derived from natural sources) — is derived from 10 priced inputs for 1 cum and works out to ₹6,518.60 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • (0.70 cum - 7.5% for voids i.e. 0.05 = 0.65
  • cum)
CodeInputUnitQuantityRate (INR)Amount (INR)
0293Stone Aggregate (Single size) : 40 mm nominal sizeMaterialcum0.651,400.00910.00
0295Stone Aggregate (Single size) : 20 mm nominal sizeMaterialcum0.241,425.00342.00
0982Coarse sand (zone III)Materialcum0.471,450.00681.50
0367Portland Cement (0.2225 cum)Portland Cement (OPC-43 Grade)Materialtonne0.135,156.00670.28
0155Mason (average)Labourday0.1857.0085.70
0114BeldarLabourday1.63736.001,199.68
0101BhistiLabourday0.7816.00571.20
0002Hire charges of Concrete Mixer 0.25 to 0.40 cum with hooperHire charges of Concrete Mixer 0.25 to 0.40 cum with HopperMachineryday0.07900.0063.00
0012Vibrator(Needle type 40mm)Vibrator (Needle type 40 mm)Machineryday0.07400.0028.00
9999SundriesMaterialL.S.13.522.2730.69
TOTAL
4,582.05
Add 1 % Water charges on “W”
45.82
TOTAL
4,627.87
Add GST on “X” (multiplying factor 0.2127)
984.35
TOTAL
5,612.22
Add 15% CPOH on “Y”
841.83
TOTAL
6,454.05
Add Cess @ 1% on “Z”
64.54
Cost of 1 cum.
6,518.59
Say
6,518.60

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 158. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.