Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level

1:5:10 (1 cement : 5 manufactured sand derived from Recycled Concrete Aggregate (RCA) : 10 graded stone aggregate 40 mm nominal size Recycled Aggregate (RA) )
Item number
4.1.10A
Analysis basis
1 cum
Priced inputs
10
Derived rate
₹4,911.85/ CUM
D-01/RATE ANALYSISITEM 4.1.10A

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.1.10A (Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:5:10 (1 cement : 5 manufactured sand derived from Recycled Concrete Aggregate (RCA) : 10 graded stone aggregate 40 mm nominal size Recycled Aggregate (RA) )) is derived from 10 priced inputs for 1 cum and works out to ₹4,911.85 per cum after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 4.1.10ADETAILS OF COST FOR 1 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0282MATRecycled Aggregate (RA) 40 mm nominal sizecum0.65390.00253.50
0283MATRecycled Aggregate (RA) 20 mm nominal sizecum0.24420.00100.80
0278MATManufactured sand derived from Recycled Concrete Aggregate (RCA)cum0.47957.00449.79
0367MATPortland Cement (0.2225 cum)Portland Cement (OPC-43 Grade)tonne0.135,156.00670.28
0155LABMason (average)day0.1857.0085.70
0114LABBeldarday1.63736.001,199.68
0101LABBhistiday0.7816.00571.20
0002MACHHire charges of Concrete Mixer 0.25 to 0.40 cum with hooperHire charges of Concrete Mixer 0.25 to 0.40 cum with Hopperday0.07900.0063.00
0012MACHVibrator(Needle type 40mm)Vibrator (Needle type 40 mm)day0.07400.0028.00
9999MATSundriesL.S.13.522.2730.69
BUILD-UP TO RATE
TOTAL
3,452.64
Add 1 % Water charges on “W”
+34.53
TOTAL
3,487.17
Add GST on “X” (multiplying factor 0.2127)
+741.72
TOTAL
4,228.89
Add 15% CPOH on “Y”
+634.33
TOTAL
4,863.22
Add Cess @ 1% on “Z”
+48.63
Cost of 1 cum.
4,911.85
SAY
₹4,911.85
D-02/SOURCEPRINTED PAGE 158
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
158

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 158. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSCONCRETE WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.