CPWD Analysis of Rates · Cladding Work

Stone tile (polished) work for wall lining over 12 mm thick bed of cement mortar 1:3 (1 cement : 3 coarse sand) and cement slurry @ 3.3 kg/sqm including pointing in white cement complete 8mm thick

Granite of any colour and shade

Item number
8.9.1.2
Analysis basis
Details of cost for 10 sqm.
Priced inputs
8
Derived rate
3,617.55 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 8.9.1.2 Stone tile (polished) work for wall lining over 12 mm thick bed of cement mortar 1:3 (1 cement : 3 coarse sand) and cement slurry @ 3.3 kg/sqm including pointing in white cement complete 8mm thick Granite of any colour and shade — is derived from 8 priced inputs for 10 sqm and works out to ₹3,617.55 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • 8mm thick Granite tiles. Qty. = 10 sqm. + Add
  • wastage @ 2.5% = 0.25 sqm. Total = 10.25 sqm.
  • Cement mortar 1:3 (1 cement : 3 coarse sand)
CodeInputUnitQuantityRate (INR)Amount (INR)
27508 mm thick granite stone tiles (mirror polished of all shades)Materialsqm10.25702.007,195.50
9977Carriage of tilesMaterialL.S.39.52.2789.67
Rate as per Item Number 3.8 of SH: MortarsRate as per item 3.8Sub-analysiscum0.144,881.95683.47
9999Mortar for pointingMaterialL.S.253.82.27576.13
0367Portland CementPortland Cement (OPC-43 Grade)Materialtonne0.0335,156.00170.15
0123Mason 1st classMason 1st classLabourday10897.008,970.00
0114BeldarLabourday10736.007,360.00
9999Sundries etc.MaterialL.S.1692.27383.63
TOTAL
25,428.55
Add 1 % Water charges on “W”
254.29
TOTAL
25,682.84
Add GST on “X” (multiplying factor 0.2127)
5,462.74
TOTAL
31,145.58
Add 15% CPOH on “Y”
4,671.84
TOTAL
35,817.42
Add Cess @ 1% on “Z”
358.17
Cost for 10 sqm.
36,175.59
Cost of 1 sqm
3,617.56
Say
3,617.55

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 393. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.