Skip to main content

CPWD Analysis of Rates · Cladding Work

Stone tile (polished) work for wall lining over 12 mm thick bed of cement mortar 1:3 (1 cement : 3 coarse sand) and cement slurry @ 3.3 kg/sqm including pointing in white cement complete 8mm thick

Raj nagar plain white marble/ Udaipur green marble/ Zebra black marble

Item number
8.9.1.1
Analysis basis
Details of cost for 10 sqm.
Priced inputs
8
Derived rate
3,190.30 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 8.9.1.1 Stone tile (polished) work for wall lining over 12 mm thick bed of cement mortar 1:3 (1 cement : 3 coarse sand) and cement slurry @ 3.3 kg/sqm including pointing in white cement complete 8mm thick Raj nagar plain white marble/ Udaipur green marble/ Zebra black marble — is derived from 8 priced inputs for 10 sqm and works out to ₹3,190.30 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • 8mm thick marble tiles. Qty. = 10 sqm. +Add
  • wastage @ 2.5% = 0.25 sqm. Total = 10.25 sqm.
  • Cement mortar 1:3 (1 cement : 3 coarse sand)
CodeInputUnitQuantityRate (INR)Amount (INR)
27518 mm thick marble tiles (polished) Raj NagarMaterialsqm10.25409.004,192.25
9977Carriage of tilesMaterialL.S.39.52.2789.67
Rate as per Item Number 3.8 of SH: MortarsRate as per item 3.8Sub-analysiscum0.144,881.95683.47
9999Mortar for pointingMaterialL.S.253.82.27576.13
0367Portland CementPortland Cement (OPC-43 Grade)Materialtonne0.0335,156.00170.15
0123Mason 1st classMason 1st classLabourday10897.008,970.00
0114BeldarLabourday10736.007,360.00
9999Sundries etc.MaterialL.S.1692.27383.63
TOTAL
22,425.30
Add 1 % Water charges on “W”
224.25
TOTAL
22,649.55
Add GST on “X” (multiplying factor 0.2127)
4,817.56
TOTAL
27,467.11
Add 15% CPOH on “Y”
4,120.07
TOTAL
31,587.18
Add Cess @ 1% on “Z”
315.87
Cost for 10 sqm.
31,903.05
Cost of 1 sqm
3,190.31
Say
3,190.30

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 393. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works