Providing and fixing expansion hold fasteners on C.C. /R.C.C./Brick masonry surface backing including drilling necessary holes and the cost of bolt etc complete. Wedge expansion type

Fastener with threaded dia 12 mm
Item number
8.8.1.3
Analysis basis
300nos. W
Priced inputs
5
Derived rate
₹61.70/ NOS. W
D-01/RATE ANALYSISITEM 8.8.1.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 8.8.1.3 (Providing and fixing expansion hold fasteners on C.C. /R.C.C./Brick masonry surface backing including drilling necessary holes and the cost of bolt etc complete. Wedge expansion type Fastener with threaded dia 12 mm) is derived from 5 priced inputs for 300nos. W and works out to ₹61.70 per nos. w after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 58.7mm length
  • Length (58.7+10mm) @ 0.05 kg./each
ANALYSIS OF RATES · ITEM 8.8.1.3DETAILS OF COST FOR 300NOS. W.E.H. FASTENER
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7432MATWedge expansion hold fastner 1/2” or 12 mmWedge expansion hold fastener 1/2” or 12 mmeach30026.007,800.00
1034MATBolts and nuts upto 300 mm in lengthBolts and nuts up to 300 mm in lengthquintal0.0755,200.00390.00
0116LABFitter (grade 1)day2.5897.002,242.50
0114LABBeldarday2.5736.001,840.00
9999MATHire and running charges for hand drill machine Sundries, drilling bit scaffolding etcL.S.3252.27737.75
BUILD-UP TO RATE
TOTAL
13,010.25
Add 1 % Water charges on “W”
+130.10
TOTAL
13,140.35
Add GST on “X” (multiplying factor 0.2127)
+2,794.95
TOTAL
15,935.30
Add 15% CPOH on “Y”
+2,390.30
TOTAL
18,325.60
Add Cess @ 1% on “Z”
+183.26
Cost for 300 nos.
18,508.86
Cost of each
61.70
SAY
₹61.70
D-02/SOURCEPRINTED PAGE 392
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
392

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 392. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.