Providing and fixing expansion hold fasteners on C.C. /R.C.C./Brick masonry surface backing including drilling necessary holes and the cost of bolt etc complete. Wedge expansion type
- Item number
- 8.8.1.3
- Analysis basis
- 300nos. W
- Priced inputs
- 5
- Derived rate
- ₹61.70/ NOS. W
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 8.8.1.3 (Providing and fixing expansion hold fasteners on C.C. /R.C.C./Brick masonry surface backing including drilling necessary holes and the cost of bolt etc complete. Wedge expansion type Fastener with threaded dia 12 mm) is derived from 5 priced inputs for 300nos. W and works out to ₹61.70 per nos. w after water charges, GST, CPOH and cess. The full build-up is below.
- 58.7mm length
- Length (58.7+10mm) @ 0.05 kg./each
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7432 | MAT | Wedge expansion hold fastner 1/2” or 12 mmWedge expansion hold fastener 1/2” or 12 mm | each | 300 | 26.00 | 7,800.00 |
| 1034 | MAT | Bolts and nuts upto 300 mm in lengthBolts and nuts up to 300 mm in length | quintal | 0.075 | 5,200.00 | 390.00 |
| 0116 | LAB | Fitter (grade 1) | day | 2.5 | 897.00 | 2,242.50 |
| 0114 | LAB | Beldar | day | 2.5 | 736.00 | 1,840.00 |
| 9999 | MAT | Hire and running charges for hand drill machine Sundries, drilling bit scaffolding etc | L.S. | 325 | 2.27 | 737.75 |
- TOTAL
- 13,010.25
- Add 1 % Water charges on “W”
- +130.10
- TOTAL
- 13,140.35
- Add GST on “X” (multiplying factor 0.2127)
- +2,794.95
- TOTAL
- 15,935.30
- Add 15% CPOH on “Y”
- +2,390.30
- TOTAL
- 18,325.60
- Add Cess @ 1% on “Z”
- +183.26
- Cost for 300 nos.
- 18,508.86
- Cost of each
- 61.70
- SAY
- ₹61.70
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 392
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 392. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.